14697 W PLUMMER ST 91402

Certificate Information: 14697 W PLUMMER ST 91402

Application / Permit
23016-20000-14620
Plan Check / Job No.
B23VN05882
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL EXISTING SFD PER ENGINEERING. FIRE SPRINKLER REQUIRD THROUGHOUT.
Permit Issued
Issued on 6/7/2023
Issuing Office
Valley
Current Status
Permit Finaled on 12/15/2023

Permit Application Status History

Submitted 5/5/2023 APPLICANT
Assigned to Plan Check Engineer 5/10/2023 ARTIN ZARUKIAN
Corrections Issued 5/13/2023 ARTIN ZARUKIAN
Building Plans Picked Up 5/15/2023 APPLICANT
Applicant returned to address corrections 6/1/2023 JESSE ARELLANO
Plan Check Approved 6/6/2023 ALEC MOUSAKHANIAN
Issued 6/7/2023 APPLICANT
Permit Finaled 12/14/2023 JENNIFER RABUCHIN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/26/2023 ROMAN GUTIERREZ
Sewer availability Cleared 5/26/2023 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Abkarian,, Raffi; Lic. No.: C36027 18763 VINTAGE STREET      NORTHRIDGE, CA 91324

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 6/15/2023 Not Ready for Inspection JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 6/16/2023 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 6/16/2023 Approved JENNIFER RABUCHIN
PLUMBING-Rough 6/16/2023 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 7/5/2023 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 7/5/2023 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 7/5/2023 Partial Inspection JENNIFER RABUCHIN
Gas Test 7/5/2023 Partial Approval JENNIFER RABUCHIN
HVAC-Rough 7/5/2023 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 7/11/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 7/11/2023 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 7/11/2023 Approved JENNIFER RABUCHIN
HVAC-Rough 7/11/2023 Approved JENNIFER RABUCHIN
Insulation 7/11/2023 Not Ready for Inspection JENNIFER RABUCHIN
Interior/Exterior Lathing 7/11/2023 Partial Approval JENNIFER RABUCHIN
Insulation 7/18/2023 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 7/24/2023 Approved JENNIFER RABUCHIN
Shower Pan 7/24/2023 Approved JENNIFER RABUCHIN
Drywall Nailing 7/27/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 11/27/2023 Corrections Issued JENNIFER RABUCHIN
Final 11/27/2023 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 11/27/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 11/27/2023 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 11/27/2023 SGSOV Not Ready JENNIFER RABUCHIN
Service/Power Release 11/27/2023 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 11/27/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 12/5/2023 Not Ready for Inspection KEVIN BERBERYAN
Final 12/5/2023 Corrections Issued KEVIN BERBERYAN
Gas Test 12/5/2023 Approved KEVIN BERBERYAN
HVAC-Final 12/5/2023 Approved KEVIN BERBERYAN
PLUMBING-Final 12/5/2023 Not Ready for Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 12/5/2023 SGSOV Approved KEVIN BERBERYAN
ELECTRICAL-Final 12/11/2023 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 12/11/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 12/11/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 12/14/2023 Approved JENNIFER RABUCHIN
Final 12/14/2023 Permit Finaled JENNIFER RABUCHIN
HVAC-Final 12/14/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 12/14/2023 Approved JENNIFER RABUCHIN