6245 N TOPANGA CANYON BLVD 91367
Certificate Information: 6245 N TOPANGA CANYON BLVD 91367
- Application / Permit
- 23016-20000-14489
- Plan Check / Job No.
- B23VN05840
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Grocery Store
- Work Description
- ePlan TI TO EXISTING GROCERY STORE
- Permit Issued
- Issued on 8/18/2023
- Issuing Office
- Current Status
- Permit Finaled on 11/1/2023
Permit Application Status History
Submitted | 5/9/2023 | APPLICANT |
Assigned to Plan Check Engineer | 5/11/2023 | SELLA BENYAMIN |
Corrections Issued | 5/16/2023 | SELLA BENYAMIN |
Quality Review Completed | 5/25/2023 | STEVEN KIM |
Plan Check Approved | 8/17/2023 | SELLA BENYAMIN |
Issued | 8/18/2023 | APPLICANT |
Permit Finaled | 11/1/2023 | BRIAN KELLY |
Permit Application Clearance Information
Specific Plan | Cleared | 6/7/2023 | SHEILA GERSHON |
DAS Clearance | Cleared | 6/22/2023 | Hernan Arreola |
Green Code | Cleared | 7/18/2023 | Hernan Arreola |
Specific Plan | Cleared | 7/20/2023 | SHEILA AHORAIAN |
Contact Information
Architect | Balzer,, David I; Lic. No.: NA38140 | , |
Contractor | ; Lic. No.: 707471-B | , |
Engineer | Holbrook,, Mollye Mikula; Lic. No.: NA6234 | , |
Inspector Information
BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Deputy Drilled-In Anchors | 8/31/2023 | Conditional Approval | DEANDRE HOFFMAN |
Excavation/Setback/Form/Re-Bar | 8/31/2023 | Approved | CAMERON CHABAN |
Deputy Reinf. Concrete | 9/5/2023 | Conditional Approval | CAMERON CHABAN |
Light Gage Steel Frame | 9/12/2023 | Approved | STEVEN LEVITT |
Drywall Nailing | 9/19/2023 | Approved | MARTIN TAVITIAN |
Smoke Detectors | 10/19/2023 | No Access for Inspection | BRIAN KELLY |
Pre-Inspection | 10/24/2023 | No Access for Inspection | BRIAN KELLY |
Final | 10/30/2023 | Not Ready for Inspection | BRIAN KELLY |
Green Building Final | 10/30/2023 | Not Ready for Inspection | BRIAN KELLY |
SGSOV-Seismic Gas S/O Valve | 10/30/2023 | SGSOV Not Ready | BRIAN KELLY |
Smoke Detectors | 10/30/2023 | Not Ready for Inspection | BRIAN KELLY |
Final | 11/1/2023 | Permit Finaled | BRIAN KELLY |
Green Building Final | 11/1/2023 | Approved | BRIAN KELLY |
SGSOV-Seismic Gas S/O Valve | 11/1/2023 | SGSOV Approved | BRIAN KELLY |
Smoke Detectors | 11/1/2023 | Approved | BRIAN KELLY |