8805 N PASO ROBLES AVE 91325

Certificate Information: 8805 N PASO ROBLES AVE 91325

Application / Permit
23016-20000-14304
Plan Check / Job No.
B23VN05776
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 25'6" X 49'11" PORTION OF (E) 27'9" X 82'7" DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). WORK TO BE DONE PER ENGINEERING.
Permit Issued
Issued on 8/25/2023
Issuing Office
Valley
Current Status
CofO Issued on 6/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/4/2023 APPLICANT
Assigned to Plan Check Engineer 5/9/2023 JESSE ARELLANO
Corrections Issued 5/9/2023 JESSE ARELLANO
Building Plans Picked Up 5/12/2023 APPLICANT
Applicant returned to address corrections 8/24/2023 MADISON ODELL
Plan Check Approved 8/24/2023 MADISON ODELL
Issued 8/25/2023 APPLICANT
CofO in Progress 5/29/2024 JAVIER RAMOS JR
Permit Finaled 6/14/2024 RUBEN SALAS
Permit Finaled 6/14/2024 RUBEN SALAS
CofO Issued 6/14/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/18/2023 MEGAN GODINEZ
Sewer availability Cleared 5/18/2023 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 5/22/2023 MEGAN GODINEZ
Construction near power lines Cleared 8/19/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Koma,, Shahram Javadi; Lic. No.: C69497 23241 VENTURA BLVD 300      WOODLAND HILLS, CA 91364

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 9/11/2023 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 9/11/2023 Corrections Issued RAUL OLAGI
Green Building Rough 9/11/2023 Not Ready for Inspection RAUL OLAGI
HVAC-Rough 9/11/2023 Corrections Issued RAUL OLAGI
PLUMBING-Rough 9/11/2023 Corrections Issued RAUL OLAGI
Sewer 9/11/2023 Not Ready for Inspection RAUL OLAGI
ELECTRICAL-Rough 11/7/2023 Approved JAVIER RAMOS JR
HVAC-Rough 11/7/2023 Approved JAVIER RAMOS JR
PLUMBING-Rough 11/7/2023 Approved JAVIER RAMOS JR
Wood Frame 11/7/2023 Partial Inspection JAVIER RAMOS JR
Deputy Wood Construction 1/29/2024 Conditional Approval ROBERT GOLD
Insulation 1/30/2024 Approved MISAEL ESPARZA
Drywall Nailing 2/6/2024 Approved MISAEL ESPARZA
Shower Pan 2/6/2024 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 2/9/2024 Approved JAVIER RAMOS JR
Green Building Rough 2/9/2024 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 2/9/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Final 5/14/2024 Approved JAVIER RAMOS JR
Final 5/14/2024 Corrections Issued JAVIER RAMOS JR
Green Building Final 5/14/2024 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 5/14/2024 SGSOV Not Ready JAVIER RAMOS JR
Smoke Detectors 5/14/2024 Approved JAVIER RAMOS JR
Final 5/17/2024 OK to Issue CofO JAVIER RAMOS JR
Gas Test 5/17/2024 Approved JAVIER RAMOS JR
HVAC-Final 5/17/2024 Approved JAVIER RAMOS JR
PLUMBING-Final 5/17/2024 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 5/17/2024 SGSOV Approved JAVIER RAMOS JR