2541 S VETERAN AVE 90064
Certificate Information: 2541 S VETERAN AVE 90064
- Application / Permit
- 23016-20000-14111
- Plan Check / Job No.
- B23VN05720
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EX DET 18'2"X18'2" GARAGE INTO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c), (d), and (g) . CONSTRUCTION DESIGN PER ENGR. EQUIPPED WITH NFPA 13-D FIRE SPRINLERS THROUGHOUT
- Permit Issued
- Issued on 5/7/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/5/2023 | HAYATO TSUCHIYA |
| Corrections Issued | 5/6/2023 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 5/9/2023 | APPLICANT |
| Plan Check Approved | 2/7/2024 | OMAR GARNICA |
| Issued | 5/7/2024 | APPLICANT |
| CofO in Progress | 4/24/2025 | ARAM AVEDISIAN |
| Permit Finaled | 4/24/2025 | RICHARD STEINBACH |
| CofO Issued | 4/24/2025 | RICHARD STEINBACH |
| Permit Finaled | 4/24/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 6/9/2023 | DINAH GARIN |
| Sewer availability | Cleared | 6/9/2023 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 6/14/2023 | ALEXANDER HELFER |
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2023 | DINAH GARIN |
| Specific Plan | Cleared | 9/12/2023 | WESTON PRINGLE |
| Construction within easement | Cleared | 12/4/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/2/2024 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 10/2/2024 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2024 | Corrections Issued | DANIEL VERA |
| Deputy Wood Construction | 10/24/2024 | Conditional Approval | MICHAEL PELHAM |
| HVAC-Rough | 10/24/2024 | Partial Approval | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 10/25/2024 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2024 | Conditional Approval | KIRK SANDERS |
| HVAC-Rough | 10/25/2024 | Approved | KIRK SANDERS |
| PLUMBING-Rough | 10/25/2024 | Corrections Issued | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2024 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 10/30/2024 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 11/6/2024 | Conditional Approval | KIRK SANDERS |
| Green Building Final | 11/6/2024 | Not Ready for Inspection | KIRK SANDERS |
| Green Building Rough | 11/6/2024 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 11/6/2024 | Partial Approval | KIRK SANDERS |
| Underground Mechanical | 11/6/2024 | Partial Approval | KIRK SANDERS |
| Verify Sprinkler Sign Off | 11/6/2024 | Approved | KIRK SANDERS |
| Insulation | 11/12/2024 | Partial Approval | REGINA MENDEZ |
| Shower Pan | 11/12/2024 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 11/15/2024 | Approved | DANIEL VERA |
| Drywall Nailing | 11/20/2024 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 4/15/2025 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Final | 4/15/2025 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 4/15/2025 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 4/17/2025 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 4/17/2025 | Approved | ARAM AVEDISIAN |
| Final | 4/17/2025 | Conditional Approval | ARAM AVEDISIAN |
| Gas Test | 4/17/2025 | Approved | ARAM AVEDISIAN |
| Green Building Final | 4/17/2025 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 4/17/2025 | SGSOV Not Required | ARAM AVEDISIAN |
| Service/Power Release | 4/17/2025 | Not Ready for Inspection | ARAM AVEDISIAN |
| Smoke Detectors | 4/17/2025 | Approved | ARAM AVEDISIAN |
| Final | 4/24/2025 | OK to Issue CofO | ARAM AVEDISIAN |