21045 W ERWIN ST 2A 91367
Certificate Information: 21045 W ERWIN ST 2A 91367
- Application / Permit
- 23016-20000-13877
- Plan Check / Job No.
- B23VN05599
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (5) Apartment
- Work Description
- eplan CHANGE OF USE FROM OFFICE TO GYM (4,130 S.F) WITH INTERIOR TENANT IMPROVEMENT.
- Permit Issued
- Issued on 8/16/2023
- Issuing Office
- Current Status
- CofO Issued on 5/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/2/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/4/2023 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 5/8/2023 | FARSHAD ALIMOHAMADI |
| Quality Review Completed | 5/8/2023 | CHARLES CHANG |
| Plan Check Approved | 7/21/2023 | FARSHAD ALIMOHAMADI |
| Issued | 8/16/2023 | APPLICANT |
| CofO in Progress | 5/23/2024 | BRIAN KELLY |
| Permit Finaled | 5/23/2024 | JEFFREY DURAN |
| CofO Issued | 5/23/2024 | JEFFREY DURAN |
| Permit Finaled | 5/23/2024 | JEFFREY DURAN |
Permit Application Clearance Information
| Sewer availability | Cleared | 5/12/2023 | DAGOVERTO GUERRERO |
| CPC | Cleared | 5/17/2023 | NATHAN ROMINE |
| Miscellaneous | Cleared | 5/17/2023 | NATHAN ROMINE |
| Miscellaneous | Cleared | 5/19/2023 | NELSON RODRIGUEZ |
| Tract Map conditions | Cleared | 5/19/2023 | NELSON RODRIGUEZ |
| ZA Case | Cleared | 5/19/2023 | NELSON RODRIGUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/23/2023 | DAGOVERTO GUERRERO |
| Specific Plan | Cleared | 7/5/2023 | SHEILA GERSHON |
| DAS Clearance | Cleared | 7/12/2023 | FARSHAD ALIMOHAMADI |
Contact Information
| Architect | Song,, Michael; Lic. No.: C32566 | 821 LIME AVENUE LONG BEACH, CA 90813 |
| Contractor | Zuma Construction Corporation; Lic. No.: 1055448-B | , |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/25/2023 | Partial Inspection | CAMERON CHABAN |
| Light Gage Steel Frame | 1/4/2024 | Not Ready for Inspection | BRIAN KELLY |
| Light Gage Steel Frame | 1/8/2024 | Not Ready for Inspection | BRIAN KELLY |
| Light Gage Steel Frame | 1/9/2024 | Not Ready for Inspection | BRIAN KELLY |
| Light Gage Steel Frame | 1/12/2024 | Conditional Approval | BRIAN KELLY |
| Light Gage Steel Frame | 1/16/2024 | No Access for Inspection | BRIAN KELLY |
| Drywall Nailing | 1/19/2024 | Approved | BRIAN KELLY |
| Drywall Nailing | 1/22/2024 | Partial Inspection | BRIAN KELLY |
| Special/Order Compliance | 1/22/2024 | Partial Inspection | MELVIN GIRTON |
| Interior/Exterior Lathing | 2/6/2024 | Not Ready for Inspection | BRIAN KELLY |
| Interior/Exterior Lathing | 2/7/2024 | Conditional Approval | BRIAN KELLY |
| Final | 4/25/2024 | Not Ready for Inspection | BRIAN KELLY |
| Reinforced Concrete Frame | 4/25/2024 | Not Ready for Inspection | BRIAN KELLY |
| Reinforced Masonry Frame | 4/25/2024 | Not Ready for Inspection | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 4/25/2024 | SGSOV Not Ready | BRIAN KELLY |
| Smoke Detectors | 4/25/2024 | Not Ready for Inspection | BRIAN KELLY |
| Final | 5/10/2024 | Not Ready for Inspection | BRIAN KELLY |
| Reinforced Concrete Frame | 5/10/2024 | Not Ready for Inspection | BRIAN KELLY |
| Reinforced Masonry Frame | 5/10/2024 | Not Ready for Inspection | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 5/10/2024 | SGSOV Not Ready | BRIAN KELLY |
| Smoke Detectors | 5/10/2024 | Not Ready for Inspection | BRIAN KELLY |
| Final | 5/14/2024 | OK to Issue CofO | BRIAN KELLY |
| Reinforced Concrete Frame | 5/14/2024 | Approved | BRIAN KELLY |
| Reinforced Masonry Frame | 5/14/2024 | Approved | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 5/14/2024 | SGSOV Approved | BRIAN KELLY |