1137 W 29TH ST 1-5 90007

Certificate Information: 1137 W 29TH ST 1-5 90007

Application / Permit
23016-20000-13767
Plan Check / Job No.
B23VN05548
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
ePlan.Convert (E) Attached carport to a 348 sf Accessory Dwelling Unir per CA Govt. Code 65852.2(e)(1)(C)
Permit Issued
Issued on 7/25/2023
Issuing Office
Current Status
CofO Issued on 7/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/3/2023 APPLICANT
Assigned to Plan Check Engineer 5/5/2023 EDWIN ESPIN
Corrections Issued 5/8/2023 EDWIN ESPIN
Applicant returned to address corrections 7/21/2023 EDWIN ESPIN
Plan Check Approved 7/25/2023 ALFREDO JARA
Issued 7/25/2023 APPLICANT
CofO in Progress 5/30/2024 ALFREDO LOPEZ
CofO Issued 7/23/2024 ERNESTO CORRAL
Permit Finaled 7/23/2024 ERNESTO CORRAL

Permit Application Clearance Information

Specific Plan Cleared 5/15/2023 WESTON PRINGLE
Address approval Cleared 5/30/2023 JESSICA OPINION
Permit Cleared 5/30/2023 JESSICA OPINION
Sewer availability Cleared 5/30/2023 JESSICA OPINION
Eng Process Fee Ord 176,300 Cleared 6/5/2023 JESSICA OPINION
HPOZ Cleared 7/19/2023 DANIEL MATA
Specific Plan Cleared 7/19/2023 DANIEL MATA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/8/2023 Approved MARTIN TAVITIAN
Floor/Roof Diaphrgm/Shear Wall 12/15/2023 Conditional Approval MARTIN TAVITIAN
Wood Frame 12/15/2023 Partial Approval MARTIN TAVITIAN
Floor/Roof Diaphrgm/Shear Wall 12/26/2023 Partial Approval JEROME BLACKWOOD
Insulation 12/26/2023 Partial Approval JEROME BLACKWOOD
Interior/Exterior Lathing 12/26/2023 Partial Approval JEROME BLACKWOOD
Drywall Nailing 12/29/2023 Approved MARTIN TAVITIAN
Final 3/8/2024 OK to Issue CofO ALFREDO LOPEZ
Green Building Final 3/8/2024 Approved ALFREDO LOPEZ
METHANE-Final 3/8/2024 Approved ALFREDO LOPEZ
SGSOV-Seismic Gas S/O Valve 3/8/2024 SGSOV Approved ALFREDO LOPEZ
Smoke Detectors 3/8/2024 Approved ALFREDO LOPEZ
Special/Order Compliance 7/3/2024 Approved ALFREDO LOPEZ