9229 N WINNETKA AVE A-B 91311
Certificate Information: 9229 N WINNETKA AVE A-B 91311
- Application / Permit
- 23016-20000-13574
- Plan Check / Job No.
- B23VN05489
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (4) Health Club
- Work Description
- CHANGE OF USE FROM (E) RESTAURANT AND BEAUTY SALON INTO 1 SPACE TO HEALTH CLUB
- Permit Issued
- Issued on 8/8/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/4/2023 | RAPHAEL ROSAS |
| Corrections Issued | 5/8/2023 | RAPHAEL ROSAS |
| Quality Review Completed | 5/11/2023 | STEVEN KIM |
| Building Plans Picked Up | 5/11/2023 | APPLICANT |
| Disabled Access Plans Picked Up | 5/15/2023 | APPLICANT |
| Applicant returned to address corrections | 7/6/2023 | RAPHAEL ROSAS |
| Plan Check Approved | 7/27/2023 | RAPHAEL ROSAS |
| Issued | 8/8/2023 | APPLICANT |
| CofO in Progress | 3/4/2024 | DEANDRE HOFFMAN |
| Permit Finaled | 3/7/2024 | JEFFREY DURAN |
| CofO Issued | 3/7/2024 | JEFFREY DURAN |
| Permit Finaled | 3/7/2024 | JEFFREY DURAN |
Permit Application Clearance Information
| Address approval | Cleared | 5/16/2023 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 5/16/2023 | LEE GUILBEAUX |
| Sewer availability | Cleared | 5/16/2023 | LEE GUILBEAUX |
| DAS Clearance | Cleared | 7/10/2023 | RAPHAEL ROSAS |
| "Q" conditions | Cleared | 7/25/2023 | NATHAN ROMINE |
| Miscellaneous | Cleared | 7/25/2023 | NATHAN ROMINE |
| Miscellaneous | Cleared | 7/25/2023 | NATHAN ROMINE |
| Tract Map conditions | Cleared | 7/25/2023 | NATHAN ROMINE |
| ZA Case | Cleared | 7/25/2023 | NATHAN ROMINE |
Contact Information
| Contractor | Wcs-Williams Construction Services; Lic. No.: 360147-B | 23682 BIRTCHER DRIVE LAKE FOREST, CA 92630 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/6/2023 | Partial Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 10/27/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Pre-Inspection | 10/30/2023 | Partial Inspection | JEFFREY FULTON |
| Insulation | 10/31/2023 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Wood Frame | 11/1/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Drywall Nailing | 11/3/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Drywall Nailing | 11/8/2023 | Approved | DEANDRE HOFFMAN |
| Partition/T-Bar Ceiling | 11/15/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Drywall Nailing | 11/22/2023 | Partial Approval | KENNETH ROBERTS |
| Pre-Inspection | 12/6/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Partition/T-Bar Ceiling | 2/8/2024 | Approved | DEANDRE HOFFMAN |
| Partition/T-Bar Ceiling | 2/9/2024 | Partial Inspection | DEANDRE HOFFMAN |
| Final | 2/23/2024 | Partial Inspection | DEANDRE HOFFMAN |
| SGSOV-Seismic Gas S/O Valve | 2/23/2024 | SGSOV Approved | DEANDRE HOFFMAN |
| Smoke Detectors | 2/23/2024 | Approved | DEANDRE HOFFMAN |
| Special/Order Compliance | 2/23/2024 | Partial Inspection | MELVIN GIRTON |
| Wood Frame | 2/23/2024 | Approved | DEANDRE HOFFMAN |
| Final | 3/4/2024 | OK to Issue CofO | DEANDRE HOFFMAN |