11275-11277 N CHIVERS AVE 91331
Certificate Information: 11275-11277 N CHIVERS AVE 91331
- Application / Permit
- 23016-20000-13498
- Plan Check / Job No.
- B23VN05460
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT GARAGE TO ATTACHED ADU PER ATTACHED ADU ORDINANCE AND DETACHED ADU TO SFD PER SB9 TWO UNIT DEVELOPMENT
- Permit Issued
- Issued on 6/15/2023
- Issuing Office
- Current Status
- CofO Issued on 4/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/4/2023 | CARLOS MONTES |
| Corrections Issued | 5/9/2023 | CARLOS MONTES |
| Quality Review Completed | 5/11/2023 | GARO TELMI |
| Applicant returned to address corrections | 5/26/2023 | CARLOS MONTES |
| Plan Check Approved | 6/15/2023 | CARLOS MONTES |
| Issued | 6/15/2023 | APPLICANT |
| CofO in Progress | 4/2/2024 | JENNIFER RABUCHIN |
| Permit Finaled | 4/10/2024 | RUBEN SALAS |
| CofO Issued | 4/10/2024 | RUBEN SALAS |
| Permit Finaled | 4/10/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 5/30/2023 | BRENNEN OBETO |
| Address approval | Cleared | 6/1/2023 | NIKKI ZULUETA |
| Senate Bill 9 | Cleared | 6/1/2023 | BRENNEN OBETO |
| Eng Process Fee Ord 176,300 | Cleared | 6/5/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 6/5/2023 | NIKKI ZULUETA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/6/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 9/6/2023 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 11/21/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 11/21/2023 | Approved | MICHEL ABAJAN |
| Green Building Rough | 11/21/2023 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 11/21/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 11/21/2023 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 3/5/2024 | Approved | MICHEL ABAJAN |
| Insulation | 3/6/2024 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 3/8/2024 | Approved | MICHEL ABAJAN |
| Final | 3/12/2024 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 3/12/2024 | Corrections Issued | MATTHEW NELSON |
| Smoke Detectors | 3/12/2024 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 3/15/2024 | Approved | JENNIFER RABUCHIN |
| Final | 3/15/2024 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 3/15/2024 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 3/15/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 3/15/2024 | Approved | JENNIFER RABUCHIN |