16117 W DEVONSHIRE ST 91344
Certificate Information: 16117 W DEVONSHIRE ST 91344
- Application / Permit
- 23016-20000-13225
- Plan Check / Job No.
- B23VN05336
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DET. GARAGE CONVERT TO NEW ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 5/12/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/26/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2023 | SERGIO MUNIZ |
| Corrections Issued | 5/1/2023 | SERGIO MUNIZ |
| Building Plans Picked Up | 5/2/2023 | APPLICANT |
| Plan Check Approved | 5/12/2023 | MOHAMMAD ESMAILI |
| Issued | 5/12/2023 | APPLICANT |
| CofO in Progress | 12/14/2023 | JAVIER RAMOS JR |
| Permit Finaled | 3/1/2024 | RUBEN SALAS |
| CofO Issued | 3/1/2024 | RUBEN SALAS |
| Permit Finaled | 3/1/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/3/2023 | RYAN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 5/3/2023 | RYAN KIM |
| Sewer availability | Cleared | 5/3/2023 | RYAN KIM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/3/2023 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 7/3/2023 | Partial Approval | JAVIER RAMOS JR |
| Sewer | 7/3/2023 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 7/3/2023 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 8/4/2023 | Partial Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 8/4/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Green Building Rough | 8/4/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 8/4/2023 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 8/4/2023 | Partial Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 8/8/2023 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 8/8/2023 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 8/8/2023 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 8/14/2023 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Rough | 8/14/2023 | Approved | JAVIER RAMOS JR |
| Insulation | 8/14/2023 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 8/21/2023 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 8/21/2023 | Approved | JAVIER RAMOS JR |
| Final | 10/12/2023 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 10/12/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 10/12/2023 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 10/12/2023 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 12/14/2023 | Approved | JAVIER RAMOS JR |
| Final | 12/14/2023 | OK to Issue CofO | JAVIER RAMOS JR |
| Green Building Final | 12/14/2023 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 12/14/2023 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 12/14/2023 | Approved | JAVIER RAMOS JR |
| Service/Power Release | 12/14/2023 | Approved | JAVIER RAMOS JR |