10037-10039 N RUBIO AVE 91343

Certificate Information: 10037-10039 N RUBIO AVE 91343

Application / Permit
23016-20000-12816
Plan Check / Job No.
B23VN05217
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Junior Accessory Dwelling Unit
Work Description
CONVERT (48 S.F) PORTION OF THE (E) SINGLE FAMILY DWELLING AND (448 S.F) OF THE (E) ATTACHED GARAGE INTO A NEW JUNIOR ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A) and 65852.229.
Permit Issued
Issued on 6/29/2023
Issuing Office
Current Status
CofO Issued on 10/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/24/2023 APPLICANT
Assigned to Plan Check Engineer 4/28/2023 SARKIS HARABEDIAN
Corrections Issued 5/1/2023 SARKIS HARABEDIAN
Applicant returned to address corrections 6/8/2023 SARKIS HARABEDIAN
Plan Check Approved 6/28/2023 MIROOSH KHACHATOORIAN
Issued 6/29/2023 APPLICANT
CofO in Progress 5/3/2024 JAVIER RAMOS JR
Permit Finaled 10/12/2024 DANIEL ORRANTE
CofO Issued 10/12/2024 DANIEL ORRANTE
Permit Finaled 10/12/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 5/4/2023 NIKKI ZULUETA
Sewer availability Cleared 5/4/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 5/19/2023 DAGOVERTO GUERRERO
Grading Pre-Inspection Cleared 5/31/2023 SERGIO VALENZUELA

Contact Information

Contractor Owner-Builder       ,
Engineer Truong,, Phong; Lic. No.: C70784 20439 E CRESTLINE DRIVE      WALNUT, CA 91789

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/15/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 2/15/2024 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 2/27/2024 Corrections Issued JOHN COLEMAN
ELECTRICAL-Rough 2/27/2024 Approved JOHN COLEMAN
HVAC-Rough 2/27/2024 Corrections Issued JOHN COLEMAN
PLUMBING-Rough 2/27/2024 Approved JOHN COLEMAN
BUILDING-Rough-Frame 3/7/2024 Corrections Issued JAVIER RAMOS JR
HVAC-Rough 3/7/2024 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 3/7/2024 Partial Approval JAVIER RAMOS JR
Deputy Wood Construction 3/8/2024 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 3/11/2024 Approved JAVIER RAMOS JR
Green Building Rough 3/11/2024 Approved JAVIER RAMOS JR
Insulation 3/11/2024 Approved JAVIER RAMOS JR
Drywall Nailing 3/13/2024 Approved JAVIER RAMOS JR
Shower Pan 3/21/2024 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 3/27/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Final 4/8/2024 Approved JAVIER RAMOS JR
Final 4/8/2024 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 4/8/2024 Approved JAVIER RAMOS JR
HVAC-Final 4/8/2024 Approved JAVIER RAMOS JR
PLUMBING-Final 4/8/2024 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 4/8/2024 SGSOV Approved JAVIER RAMOS JR