1025 W 34TH ST 90089
Certificate Information: 1025 W 34TH ST 90089
- Application / Permit
- 23016-20000-12745
- Plan Check / Job No.
- B23VN05187
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- ePlan ***TENANT IMPROVEMENT FOR CHANGE OF USE FROM JUICE BAR TO FOOD PANTRY RETAIL AND OFFICE IN AN EXISTING BLDG. WORK WILL INCLUDE MINOR DEMOLITION NON STRUCTURAL, NEW PARTITIONS, MILLWORK, INTERIOR DOORS, CEILINGS
- Permit Issued
- Issued on 12/12/2023
- Issuing Office
- Current Status
- CofO Issued on 1/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/27/2023 | SINA KHOSRAVI |
| Corrections Issued | 5/1/2023 | SINA KHOSRAVI |
| Quality Review Completed | 5/11/2023 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 12/8/2023 | SINA KHOSRAVI |
| Issued | 12/12/2023 | APPLICANT |
| CofO in Progress | 1/7/2025 | ALFREDO LOPEZ |
| CofO Issued | 1/7/2025 | ERNESTO CORRAL |
| Permit Finaled | 1/7/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| DAS Clearance | Cleared | 5/14/2023 | SINA KHOSRAVI |
| CPC | Cleared | 5/17/2023 | RYAN LY |
| ZA Case | Cleared | 5/17/2023 | RYAN LY |
| ZI | Cleared | 5/17/2023 | SUSAN WONG |
| Eng Process Fee Ord 176,300 | Cleared | 6/1/2023 | WALLIE JONG |
| Specific Plan | Cleared | 6/14/2023 | RAFAEL FONTES |
| ZI | Cleared | 6/14/2023 | RAFAEL FONTES |
| Sewer availability | Cleared | 6/21/2023 | WALLIE JONG |
Contact Information
| Architect | Nouizi,, Ilyes M; Lic. No.: NA32135 | , |
| Contractor | H C Olsen Construction Co Inc; Lic. No.: 177029-B | 710 E LOS ANGELES ST MONROVIA, CA 91016 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 2/20/2024 | Conditional Approval | MARTIN TAVITIAN |
| Insulation | 3/5/2024 | Partial Approval | ALFREDO LOPEZ |
| Light Gage Steel Frame | 3/5/2024 | Partial Approval | ALFREDO LOPEZ |
| Drywall Nailing | 3/11/2024 | Partial Approval | ALFREDO LOPEZ |
| Drywall Nailing | 4/19/2024 | Partial Approval | RONALD JIMENEZ |
| T-Bar Ceiling | 5/2/2024 | Partial Approval | ALFREDO LOPEZ |
| Final | 7/15/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| METHANE-Final | 7/15/2024 | Approved | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 7/15/2024 | SGSOV Approved | ALFREDO LOPEZ |
| Smoke Detectors | 7/15/2024 | Approved | ALFREDO LOPEZ |
| Final | 7/22/2024 | Conditional Approval | ALFREDO LOPEZ |
| Final | 10/22/2024 | OK to Issue CofO | ALFREDO LOPEZ |