6530 N GLORIA AVE 91406
Certificate Information: 6530 N GLORIA AVE 91406
- Application / Permit
- 23016-20000-12627
- Plan Check / Job No.
- B23VN05163
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN: CONVERT (E) 21'-2" X 83'-9" DETACHED STORAGE TO (N) DETACHED ACCESSORY DWELLING UNIT PER PER GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 6/14/2023
- Issuing Office
- Current Status
- CofO Issued on 2/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2023 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 4/29/2023 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 6/8/2023 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 6/13/2023 | GURUNATH NESARAJAH |
| Issued | 6/14/2023 | APPLICANT |
| CofO in Progress | 1/18/2024 | RAUL OLAGI |
| Permit Finaled | 2/15/2024 | RUBEN SALAS |
| CofO Issued | 2/15/2024 | RUBEN SALAS |
| Permit Finaled | 2/15/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/2/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 5/2/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 5/11/2023 | DAGOVERTO GUERRERO |
| Hold | Cleared | 7/13/2023 | MARIA VENDIVIL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 7/24/2023 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 7/24/2023 | Partial Inspection | RAUL OLAGI |
| HVAC-Rough | 7/24/2023 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 7/24/2023 | Partial Inspection | RAUL OLAGI |
| Sewer | 7/24/2023 | Approved | RAUL OLAGI |
| Underground Mechanical | 7/24/2023 | Partial Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 8/2/2023 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 8/2/2023 | Approved | RAUL OLAGI |
| HVAC-Rough | 8/2/2023 | Corrections Issued | RAUL OLAGI |
| Insulation | 8/2/2023 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 8/2/2023 | Approved | RAUL OLAGI |
| Underground Mechanical | 8/2/2023 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 8/15/2023 | Not Ready for Inspection | RAUL OLAGI |
| HVAC-Rough | 8/15/2023 | Corrections Issued | RAUL OLAGI |
| Insulation | 8/15/2023 | Not Ready for Inspection | RAUL OLAGI |
| BUILDING-Rough-Frame | 8/21/2023 | Approved | RAUL OLAGI |
| HVAC-Rough | 8/21/2023 | Approved | RAUL OLAGI |
| Insulation | 8/21/2023 | Approved | RAUL OLAGI |
| Drywall Nailing | 8/24/2023 | Approved | RAUL OLAGI |
| Shower Pan | 9/14/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 9/27/2023 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 12/28/2023 | Corrections Issued | RAUL OLAGI |
| HVAC-Final | 12/28/2023 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Final | 12/28/2023 | Corrections Issued | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 12/28/2023 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 12/28/2023 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 1/10/2024 | Approved | RAUL OLAGI |
| HVAC-Final | 1/10/2024 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Final | 1/10/2024 | Approved | RAUL OLAGI |
| Final | 1/17/2024 | OK to Issue CofO | RAUL OLAGI |
| HVAC-Final | 1/17/2024 | Approved | RAUL OLAGI |