14630 W HAMLIN ST 91411

Certificate Information: 14630 W HAMLIN ST 91411

Application / Permit
23016-20000-12625
Plan Check / Job No.
B23VN05161
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 22' X 30' DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). DESIGN PER ENGINEERING.
Permit Issued
Issued on 6/8/2023
Issuing Office
Current Status
CofO Issued on 4/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/22/2023 APPLICANT
Assigned to Plan Check Engineer 4/27/2023 OMAR GARNICA
Corrections Issued 4/28/2023 OMAR GARNICA
Applicant returned to address corrections 5/26/2023 SARKIS HARABEDIAN
Plan Check Approved 6/8/2023 SARKIS HARABEDIAN
Issued 6/8/2023 APPLICANT
CofO in Progress 3/5/2024 RYAN SALAZAR
Permit Finaled 4/3/2024 DANIEL ORRANTE
Permit Finaled 4/3/2024 DANIEL ORRANTE
CofO Issued 4/3/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 5/9/2023 ROMAN GUTIERREZ
Sewer availability Cleared 5/9/2023 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 5/18/2023 ROMAN GUTIERREZ
HPOZ Cleared 6/5/2023 ERIK VAN BREENE

Contact Information

Contractor Owner-Builder       ,
Engineer Nazarians,, Harmick; Lic. No.: C91232 9825 OSO AVE      CHATSWORTH, CA 91311

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/10/2023 Corrections Issued RYAN SALAZAR
PLUMBING-Rough 7/10/2023 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 8/4/2023 Corrections Issued MISAEL ESPARZA
Wood Frame 8/4/2023 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 8/17/2023 Conditional Approval RYAN SALAZAR
HVAC-Rough 8/17/2023 Approved RYAN SALAZAR
PLUMBING-Rough 8/17/2023 Approved RYAN SALAZAR
Wood Frame 8/17/2023 Corrections Issued RYAN SALAZAR
Insulation 9/1/2023 Conditional Approval MISAEL ESPARZA
Interior/Exterior Lathing 9/1/2023 Conditional Approval MISAEL ESPARZA
Drywall Nailing 9/18/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 10/2/2023 Approved ROBERT GOLD
Shower Pan 10/2/2023 Approved ROBERT GOLD
BUILDING-Rough-Frame 2/16/2024 No Access for Inspection CRAIG DAVIS
Final 2/16/2024 No Access for Inspection CRAIG DAVIS
Green Building Final 2/16/2024 No Access for Inspection CRAIG DAVIS
Green Building Rough 2/16/2024 No Access for Inspection CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 2/16/2024 SGSOV Not Ready CRAIG DAVIS
Smoke Detectors 2/16/2024 No Access for Inspection CRAIG DAVIS
BUILDING-Rough-Frame 2/23/2024 Approved RYAN SALAZAR
Final 2/23/2024 Partial Inspection RYAN SALAZAR
Green Building Final 2/23/2024 Approved RYAN SALAZAR
Green Building Rough 2/23/2024 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 2/23/2024 SGSOV Approved RYAN SALAZAR
Smoke Detectors 2/23/2024 Partial Approval RYAN SALAZAR
Final 3/5/2024 OK to Issue CofO RYAN SALAZAR
Smoke Detectors 3/5/2024 Approved RYAN SALAZAR