14630 W HAMLIN ST 91411
Certificate Information: 14630 W HAMLIN ST 91411
- Application / Permit
- 23016-20000-12625
- Plan Check / Job No.
- B23VN05161
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 22' X 30' DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). DESIGN PER ENGINEERING.
- Permit Issued
- Issued on 6/8/2023
- Issuing Office
- Current Status
- CofO Issued on 4/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/27/2023 | OMAR GARNICA |
| Corrections Issued | 4/28/2023 | OMAR GARNICA |
| Applicant returned to address corrections | 5/26/2023 | SARKIS HARABEDIAN |
| Plan Check Approved | 6/8/2023 | SARKIS HARABEDIAN |
| Issued | 6/8/2023 | APPLICANT |
| CofO in Progress | 3/5/2024 | RYAN SALAZAR |
| Permit Finaled | 4/3/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/3/2024 | DANIEL ORRANTE |
| CofO Issued | 4/3/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 5/9/2023 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 5/9/2023 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/18/2023 | ROMAN GUTIERREZ |
| HPOZ | Cleared | 6/5/2023 | ERIK VAN BREENE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nazarians,, Harmick; Lic. No.: C91232 | 9825 OSO AVE CHATSWORTH, CA 91311 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/10/2023 | Corrections Issued | RYAN SALAZAR |
| PLUMBING-Rough | 7/10/2023 | Partial Approval | RYAN SALAZAR |
| ELECTRICAL-Rough | 8/4/2023 | Corrections Issued | MISAEL ESPARZA |
| Wood Frame | 8/4/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 8/17/2023 | Conditional Approval | RYAN SALAZAR |
| HVAC-Rough | 8/17/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 8/17/2023 | Approved | RYAN SALAZAR |
| Wood Frame | 8/17/2023 | Corrections Issued | RYAN SALAZAR |
| Insulation | 9/1/2023 | Conditional Approval | MISAEL ESPARZA |
| Interior/Exterior Lathing | 9/1/2023 | Conditional Approval | MISAEL ESPARZA |
| Drywall Nailing | 9/18/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 10/2/2023 | Approved | ROBERT GOLD |
| Shower Pan | 10/2/2023 | Approved | ROBERT GOLD |
| BUILDING-Rough-Frame | 2/16/2024 | No Access for Inspection | CRAIG DAVIS |
| Final | 2/16/2024 | No Access for Inspection | CRAIG DAVIS |
| Green Building Final | 2/16/2024 | No Access for Inspection | CRAIG DAVIS |
| Green Building Rough | 2/16/2024 | No Access for Inspection | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 2/16/2024 | SGSOV Not Ready | CRAIG DAVIS |
| Smoke Detectors | 2/16/2024 | No Access for Inspection | CRAIG DAVIS |
| BUILDING-Rough-Frame | 2/23/2024 | Approved | RYAN SALAZAR |
| Final | 2/23/2024 | Partial Inspection | RYAN SALAZAR |
| Green Building Final | 2/23/2024 | Approved | RYAN SALAZAR |
| Green Building Rough | 2/23/2024 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 2/23/2024 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 2/23/2024 | Partial Approval | RYAN SALAZAR |
| Final | 3/5/2024 | OK to Issue CofO | RYAN SALAZAR |
| Smoke Detectors | 3/5/2024 | Approved | RYAN SALAZAR |