7900-7902 N JELLICO AVE 91325
Certificate Information: 7900-7902 N JELLICO AVE 91325
- Application / Permit
- 23016-20000-12572
- Plan Check / Job No.
- B23VN05151
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE AND (E) 9' X 8' PORTION OF SFD TO (N) JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). WORK DONE PER WFPP.
- Permit Issued
- Issued on 5/16/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/25/2023 | JESSE ARELLANO |
| Corrections Issued | 4/26/2023 | JESSE ARELLANO |
| Building Plans Picked Up | 4/27/2023 | APPLICANT |
| Applicant returned to address corrections | 5/8/2023 | MADISON ODELL |
| Plan Check Approved | 5/16/2023 | SERGIO MUNIZ |
| Issued | 5/16/2023 | APPLICANT |
| CofO in Progress | 5/31/2024 | RAUL OLAGI |
| Permit Finaled | 6/25/2024 | RUBEN SALAS |
| CofO Issued | 6/25/2024 | RUBEN SALAS |
| Permit Finaled | 6/25/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/2/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 5/2/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 5/2/2023 | NIKKI ZULUETA |
Contact Information
| Contractor | Davudians Jorjik; Lic. No.: 928686-B | 23345 SANDALWOOD STREET WEST HILLS, CA 91307 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/14/2023 | Corrections Issued | RAUL OLAGI |
| Sewer | 6/14/2023 | Approved | RAUL OLAGI |
| Special/Order Compliance | 6/14/2023 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 6/22/2023 | Approved | RAUL OLAGI |
| Sewer | 6/22/2023 | Approved | RAUL OLAGI |
| Footing/Foundation/Slab | 6/29/2023 | Partial Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 7/3/2023 | Partial Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 7/7/2023 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2023 | Partial Approval | RAUL OLAGI |
| Interior/Exterior Lathing | 8/8/2023 | Partial Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 10/11/2023 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 10/11/2023 | Approved | RAUL OLAGI |
| HVAC-Rough | 10/11/2023 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 10/11/2023 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 10/24/2023 | Partial Approval | RAUL OLAGI |
| Green Building Rough | 10/24/2023 | Approved | RAUL OLAGI |
| Insulation | 10/24/2023 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2023 | Approved | RAUL OLAGI |
| Shower Pan | 10/26/2023 | Approved | RAUL OLAGI |
| Drywall Nailing | 11/6/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 11/6/2023 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 5/23/2024 | Approved | RAUL OLAGI |
| Final | 5/23/2024 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 5/23/2024 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 5/23/2024 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 5/23/2024 | Approved | RAUL OLAGI |
| Final | 5/30/2024 | OK to Issue CofO | RAUL OLAGI |