11220-11222 N COMETA AVE 91331

Certificate Information: 11220-11222 N COMETA AVE 91331

Application / Permit
23016-20000-12479
Plan Check / Job No.
B23VN05113
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT THE (E) TWO CAR ATTACHED GARAGE INTO JUNIOR ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A) and 65852.229. WORK PER WFPP.
Permit Issued
Issued on 6/1/2023
Issuing Office
Current Status
CofO Issued on 8/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/20/2023 APPLICANT
Assigned to Plan Check Engineer 4/26/2023 AMY GUEVARRA
Corrections Issued 4/27/2023 AMY GUEVARRA
Plan Check Approved 6/1/2023 SARKIS HARABEDIAN
Issued 6/1/2023 APPLICANT
CofO in Progress 7/30/2024 MICHEL ABAJAN
Permit Finaled 8/14/2024 DANIEL ORRANTE
CofO Issued 8/14/2024 DANIEL ORRANTE
Permit Finaled 8/14/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 5/2/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 5/2/2023 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 5/2/2023 CARLOS AGUILERA
Sewer availability Cleared 5/2/2023 CARLOS AGUILERA
Grading Pre-Inspection Cleared 5/9/2023 BRIAN MILLER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/27/2023 Partial Inspection MICHEL ABAJAN
Deputy Drilled-In Anchors 8/7/2023 Conditional Approval ROBERT GOLD
Deputy Drilled-In Anchors 8/14/2023 Approved MICHEL ABAJAN
Footing/Foundation/Slab 8/17/2023 Conditional Approval ROBERT GOLD
PLUMBING-Rough 8/17/2023 Corrections Issued ROBERT GOLD
Sewer 8/17/2023 Approved ROBERT GOLD
Footing/Foundation/Slab 8/25/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 8/25/2023 Corrections Issued MICHEL ABAJAN
BUILDING-Rough-Frame 9/25/2023 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 9/25/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 9/25/2023 Not Ready for Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 10/6/2023 Approved MICHEL ABAJAN
Green Building Rough 10/6/2023 Approved MICHEL ABAJAN
Rough-Elec/Plmb/HVAC 10/6/2023 Approved MICHEL ABAJAN
Insulation 10/16/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 10/16/2023 Approved MICHEL ABAJAN
Drywall Nailing 10/27/2023 Approved MICHEL ABAJAN
ELECTRICAL-Final 6/20/2024 Approved MICHEL ABAJAN
Final 6/20/2024 Corrections Issued MICHEL ABAJAN
HVAC-Final 6/20/2024 Approved MICHEL ABAJAN
PLUMBING-Final 6/20/2024 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 6/20/2024 SGSOV Not Ready MICHEL ABAJAN
Smoke Detectors 6/20/2024 Approved MICHEL ABAJAN
Final 7/29/2024 Corrections Issued MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 7/29/2024 SGSOV Approved MICHEL ABAJAN
Final 7/30/2024 OK to Issue CofO MICHEL ABAJAN