307 N ARDEN BLVD 90004

Certificate Information: 307 N ARDEN BLVD 90004

Application / Permit
23016-20000-12271
Plan Check / Job No.
B23VN05042
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) 20'-0" x 20'-0" DETACHED GARAGE INTO A NEW ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A).
Permit Issued
Issued on 10/4/2023
Issuing Office
Valley
Current Status
CofO Issued on 3/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/19/2023 APPLICANT
Assigned to Plan Check Engineer 4/21/2023 SERGIO MUNIZ
Corrections Issued 4/22/2023 SERGIO MUNIZ
Building Plans Picked Up 4/28/2023 APPLICANT
Plan Check Approved 10/4/2023 SARKIS HARABEDIAN
Issued 10/4/2023 APPLICANT
CofO in Progress 3/1/2024 JEFFREY MEAD
Permit Finaled 3/5/2024 DEROLD HAUFF
CofO Issued 3/5/2024 DEROLD HAUFF
Permit Finaled 3/5/2024 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 6/20/2023 HUGO LOPEZ
Address approval Cleared 6/21/2023 HUGO LOPEZ
Eng Process Fee Ord 176,300 Cleared 6/21/2023 HUGO LOPEZ
Construction near power lines Cleared 9/23/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/10/2023 Approved JEFFREY MEAD
Underground Mechanical 10/10/2023 Approved JEFFREY MEAD
Footing/Foundation/Slab 10/18/2023 Partial Approval JEFFREY MEAD
Deputy Drilled-In Anchors 10/23/2023 Conditional Approval JEFFREY MEAD
Footing/Foundation/Slab 10/23/2023 Approved JEFFREY MEAD
ELECTRICAL-Rough 11/3/2023 Corrections Issued JEFFREY MEAD
PLUMBING-Rough 11/3/2023 Approved JEFFREY MEAD
BUILDING-Rough-Frame 11/6/2023 Corrections Issued JEFFREY MEAD
ELECTRICAL-Rough 11/6/2023 Approved JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 11/6/2023 Approved JEFFREY MEAD
HVAC-Rough 11/6/2023 Approved JEFFREY MEAD
Interior/Exterior Lathing 11/6/2023 Not Ready for Inspection JEFFREY MEAD
Shower Pan 11/6/2023 Not Ready for Inspection JEFFREY MEAD
BUILDING-Rough-Frame 11/7/2023 Approved JEFFREY MEAD
Green Building Rough 11/7/2023 Approved JEFFREY MEAD
Insulation 11/7/2023 Approved JEFFREY MEAD
Interior/Exterior Lathing 11/7/2023 Partial Approval JEFFREY MEAD
METHANE-Rough 11/7/2023 Approved JEFFREY MEAD
Shower Pan 11/7/2023 Not Ready for Inspection JEFFREY MEAD
Interior/Exterior Lathing 11/8/2023 Approved JEFFREY MEAD
Drywall Nailing 11/13/2023 Approved JEFFREY MEAD
Underground Mechanical 12/6/2023 Partial Approval JEFFREY MEAD
Underground Mechanical 12/12/2023 Approved JEFFREY MEAD
Final 2/15/2024 Corrections Issued JEFFREY MEAD
Green Building Final 2/15/2024 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 2/15/2024 SGSOV Not Ready JEFFREY MEAD
Smoke Detectors 2/15/2024 Approved JEFFREY MEAD
ELECTRICAL-Final 2/22/2024 Approved JEFFREY MEAD
Final 2/22/2024 Partial Approval JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 2/22/2024 SGSOV Approved JEFFREY MEAD
Final 2/27/2024 OK to Issue CofO JEFFREY MEAD