8620-8622 N NOBLE AVE 91343

Certificate Information: 8620-8622 N NOBLE AVE 91343

Application / Permit
23016-20000-12199
Plan Check / Job No.
B23VN05014
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT PORTION OF EX. SFD AND ENCLOSE PATIO COVER INTO JUNIOR ACCESSORY DWELLING UNIT ( 410 SF ) PER GCS 65852.2(e)(1)(A) AND 65852.22. WORK PER ENGINEER.
Permit Issued
Issued on 5/4/2023
Issuing Office
Valley
Current Status
CofO Issued on 6/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/19/2023 APPLICANT
Assigned to Plan Check Engineer 4/21/2023 JESSE ARELLANO
Corrections Issued 4/22/2023 JESSE ARELLANO
Building Plans Picked Up 4/25/2023 APPLICANT
Plan Check Approved 5/4/2023 ROSENDO MEDINA
Issued 5/4/2023 APPLICANT
CofO in Progress 6/12/2024 VINCENT HANLEY
Permit Finaled 6/24/2024 RUBEN SALAS
CofO Issued 6/24/2024 RUBEN SALAS
Permit Finaled 6/24/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/2/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 5/2/2023 NIKKI ZULUETA
Sewer availability Cleared 5/2/2023 NIKKI ZULUETA
Tract Map conditions Cleared 5/3/2023 ASHLEY RODARTE

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21757 DEVONSHIRE ST.   SUITE 3    CANOGA PARK, CA 91311

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/12/2023 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 5/15/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 5/19/2023 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 5/19/2023 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 5/25/2023 Partial Approval CHRISTOPHER DELLEFIELD
Underground Mechanical 5/25/2023 Partial Approval CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 5/30/2023 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 6/8/2023 Not Ready for Inspection MATTHEW NELSON
Green Building Rough 6/8/2023 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Rough 6/15/2023 Approved DAVID MATSON
PLUMBING-Rough 6/15/2023 Approved DAVID MATSON
BUILDING-Rough-Frame 6/22/2023 Corrections Issued GREGG CUMMINGS
HVAC-Rough 6/22/2023 Corrections Issued GREGG CUMMINGS
BUILDING-Rough-Frame 6/26/2023 No Access for Inspection RAUL OLAGI
Green Building Rough 6/26/2023 No Access for Inspection RAUL OLAGI
Insulation 6/26/2023 No Access for Inspection RAUL OLAGI
Shower Pan 6/26/2023 No Access for Inspection RAUL OLAGI
BUILDING-Rough-Frame 6/29/2023 Partial Approval MATTHEW NELSON
Green Building Rough 6/29/2023 Approved MATTHEW NELSON
Shower Pan 6/29/2023 Approved MATTHEW NELSON
Insulation 7/3/2023 Approved GREGG CUMMINGS
Interior/Exterior Lathing 7/3/2023 Partial Approval GREGG CUMMINGS
Drywall Nailing 7/11/2023 Approved GREGG CUMMINGS
Interior/Exterior Lathing 7/11/2023 Partial Approval GREGG CUMMINGS
BUILDING-Rough-Frame 10/23/2023 Approved GREGG CUMMINGS
Final 10/23/2023 Corrections Issued GREGG CUMMINGS
Green Building Final 10/23/2023 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 10/23/2023 SGSOV Not Ready GREGG CUMMINGS
Smoke Detectors 10/23/2023 Not Ready for Inspection GREGG CUMMINGS
Final 11/2/2023 Not Ready for Inspection RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 11/2/2023 SGSOV Not Ready RAUL BARAJAS
Smoke Detectors 11/2/2023 Partial Inspection RAUL BARAJAS
Final 1/18/2024 Not Ready for Inspection GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 1/18/2024 SGSOV Not Ready GREGG CUMMINGS
Smoke Detectors 1/18/2024 Not Ready for Inspection GREGG CUMMINGS
Final 1/23/2024 Corrections Issued GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 1/23/2024 SGSOV Approved GREGG CUMMINGS
Smoke Detectors 1/23/2024 Not Ready for Inspection GREGG CUMMINGS
Final 4/18/2024 Corrections Issued KIRK SANDERS
Smoke Detectors 4/18/2024 Approved KIRK SANDERS
Final 5/7/2024 Partial Approval KIRK SANDERS
ELECTRICAL-Final 6/11/2024 Approved VINCENT HANLEY
Final 6/11/2024 OK to Issue CofO VINCENT HANLEY
HVAC-Final 6/11/2024 Approved VINCENT HANLEY
PLUMBING-Final 6/11/2024 Approved VINCENT HANLEY
Service/Power Release 6/11/2024 Approved VINCENT HANLEY