13438 N BRADLEY AVE 91342

Certificate Information: 13438 N BRADLEY AVE 91342

Application / Permit
23016-20000-12132
Plan Check / Job No.
B23VN05000
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(eplan) CONVERTING EXISTING GARAGE TO NEW ACCESSORY DWELLING UNIT AND REMODELING PER CA Govt. Code 65852.2(e)(1)(A).
Permit Issued
Issued on 10/18/2023
Issuing Office
Current Status
CofO Issued on 8/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/18/2023 APPLICANT
Assigned to Plan Check Engineer 5/4/2023 YOUNG KIM
Corrections Issued 5/19/2023 YOUNG KIM
Quality Review Completed 5/25/2023 FARUK SEZER
Applicant returned to address corrections 6/28/2023 YOUNG KIM
Applicant returned to address corrections 7/12/2023 YOUNG KIM
Applicant returned to address corrections 8/2/2023 YOUNG KIM
Applicant returned to address corrections 8/3/2023 YOUNG KIM
Applicant returned to address corrections 9/27/2023 YOUNG KIM
Applicant returned to address corrections 9/28/2023 YOUNG KIM
Applicant returned to address corrections 10/11/2023 YOUNG KIM
Plan Check Approved 10/12/2023 YOUNG KIM
Issued 10/18/2023 APPLICANT
CofO in Progress 8/8/2025 KEVIN BERBERYAN
Permit Finaled 8/13/2025 RUBEN SALAS
CofO Issued 8/13/2025 RUBEN SALAS
Permit Finaled 8/13/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/25/2023 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 7/21/2023 ROMAN GUTIERREZ
Sewer availability Cleared 7/25/2023 ROMAN GUTIERREZ
Grading Pre-Inspection Cleared 8/1/2023 ALEXANDER HELFER
ZI Cleared 8/21/2023 RYAN LY

Contact Information

Contractor Owner-Builder       ,
Engineer Carrillo,, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/30/2023 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 12/26/2023 Corrections Issued KEVIN BERBERYAN
PLUMBING-Rough 12/26/2023 Corrections Issued KEVIN BERBERYAN
Excavation/Setback/Form/Re-Bar 1/4/2024 Not Ready for Inspection KEVIN BERBERYAN
PLUMBING-Rough 1/4/2024 Approved KEVIN BERBERYAN
Footing/Foundation/Slab 1/12/2024 Approved KEVIN BERBERYAN
PLUMBING-Rough 1/12/2024 Partial Inspection KEVIN BERBERYAN
ELECTRICAL-Rough 1/26/2024 Corrections Issued CHRISTOPHER ROJAS
HVAC-Rough 1/26/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Insulation 1/26/2024 Partial Approval CHRISTOPHER ROJAS
ELECTRICAL-Rough 2/1/2024 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 2/1/2024 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 2/2/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Rough 2/2/2024 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 2/2/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Insulation 2/2/2024 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 2/9/2024 Corrections Issued JOHN COLEMAN
ELECTRICAL-Rough 2/9/2024 Corrections Issued JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 2/9/2024 Not Ready for Inspection JOHN COLEMAN
Green Building Rough 2/9/2024 Not Ready for Inspection JOHN COLEMAN
BUILDING-Rough-Frame 2/14/2024 Corrections Issued JOHN COLEMAN
ELECTRICAL-Rough 2/14/2024 Approved JOHN COLEMAN
Shower Pan 2/14/2024 Not Ready for Inspection JOHN COLEMAN
BUILDING-Rough-Frame 2/20/2024 Not Ready for Inspection CRAIG DAVIS
Green Building Rough 2/20/2024 Corrections Issued CRAIG DAVIS
HVAC-Rough 2/20/2024 Corrections Issued CRAIG DAVIS
Interior/Exterior Lathing 2/20/2024 Not Ready for Inspection CRAIG DAVIS
Shower Pan 2/20/2024 Corrections Issued CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 2/22/2024 Approved CHRISTOPHER ROJAS
Shower Pan 2/22/2024 Corrections Issued CHRISTOPHER ROJAS
Deputy Wood Construction 2/23/2024 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 2/27/2024 Approved KEVIN BERBERYAN
Green Building Rough 2/27/2024 Not Ready for Inspection KEVIN BERBERYAN
Interior/Exterior Lathing 2/27/2024 Approved KEVIN BERBERYAN
Shower Pan 2/27/2024 Approved KEVIN BERBERYAN
HVAC-Rough 4/16/2024 Approved KEVIN BERBERYAN
Insulation 4/16/2024 Conditional Approval KEVIN BERBERYAN
Drywall Nailing 4/24/2024 Approved KEVIN BERBERYAN
Insulation 4/24/2024 Approved KEVIN BERBERYAN
Sewer 8/6/2024 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 9/19/2024 Not Ready for Inspection KEVIN BERBERYAN
Final 9/19/2024 Not Ready for Inspection KEVIN BERBERYAN
Green Building Final 9/19/2024 Not Ready for Inspection KEVIN BERBERYAN
Green Building Rough 9/19/2024 Not Ready for Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 9/19/2024 No Access for Inspection KEVIN BERBERYAN
Smoke Detectors 9/19/2024 Not Ready for Inspection KEVIN BERBERYAN
Service/Power Release 11/22/2024 Corrections Issued KEVIN BERBERYAN
BUILDING-Rough-Frame 2/25/2025 Approved KEVIN BERBERYAN
Final 2/25/2025 Corrections Issued KEVIN BERBERYAN
Green Building Final 2/25/2025 Not Ready for Inspection KEVIN BERBERYAN
Green Building Rough 2/25/2025 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 2/25/2025 SGSOV Approved KEVIN BERBERYAN
Smoke Detectors 2/25/2025 Approved KEVIN BERBERYAN
Final 3/20/2025 Partial Inspection KEVIN BERBERYAN
Green Building Final 3/20/2025 Not Ready for Inspection KEVIN BERBERYAN
Final 8/8/2025 OK to Issue CofO KEVIN BERBERYAN
Green Building Final 8/8/2025 Approved KEVIN BERBERYAN