10173 N MAUDE AVE 91040

Certificate Information: 10173 N MAUDE AVE 91040

Application / Permit
23016-20000-11962
Plan Check / Job No.
B23VN04893
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan CONVERTING EXISTING 30'X38' 3 CAR GARAGE TO ADU. Per CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 7/21/2023
Issuing Office
Current Status
CofO Issued on 4/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/17/2023 APPLICANT
Assigned to Plan Check Engineer 4/21/2023 ALFREDO JARA
Corrections Issued 4/22/2023 ALFREDO JARA
Plan Check Approved 7/19/2023 ALFREDO JARA
Issued 7/21/2023 APPLICANT
CofO in Progress 2/15/2024 DAVID ANDERSON
Permit Finaled 4/3/2024 RUBEN SALAS
CofO Issued 4/3/2024 RUBEN SALAS
Permit Finaled 4/3/2024 RUBEN SALAS

Permit Application Clearance Information

Specific Plan Cleared 5/5/2023 CECILIA CASTILLO
Hydrant and Access approval Cleared 5/24/2023 MATTHEW CRAIG
Address approval Cleared 6/6/2023 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 6/6/2023 TAL SHEMEN
Roof/Waste drainage to street Cleared 6/6/2023 TAL SHEMEN
Sewer availability Cleared 6/6/2023 TAL SHEMEN
ZI Cleared 6/6/2023 NATHAN ROMINE
Grading Pre-Inspection Cleared 7/19/2023 ALFREDO JARA

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/25/2023 Approved DAVID ANDERSON
Footing/Foundation/Slab 9/14/2023 Approved DAVID ANDERSON
PLUMBING-Rough 9/14/2023 Partial Approval DAVID ANDERSON
Deputy Drilled-In Anchors 9/26/2023 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 10/5/2023 Corrections Issued DAVID ANDERSON
Deputy Wood Construction 10/10/2023 Conditional Approval DAVID MATSON
Deputy Drilled-In Anchors 10/25/2023 Conditional Approval ROBERT GOLD
Deputy Wood Construction 10/30/2023 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 11/3/2023 Partial Approval CHRISTOPHER ROJAS
Interior/Exterior Lathing 11/3/2023 Partial Approval CHRISTOPHER ROJAS
Rough-Elec/Plmb/HVAC 11/3/2023 Corrections Issued CHRISTOPHER ROJAS
Rough-Elec/Plmb/HVAC 11/8/2023 Approved DAVID ANDERSON
Insulation 12/7/2023 Approved WILLIAM WREN
Drywall Nailing 12/13/2023 Approved DAVID ANDERSON
Shower Pan 12/13/2023 Approved DAVID ANDERSON
Interior/Exterior Lathing 12/19/2023 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 2/7/2024 Approved DAVID ANDERSON
Final 2/7/2024 Not Ready for Inspection DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 2/7/2024 SGSOV Approved DAVID ANDERSON
Smoke Detectors 2/7/2024 Approved DAVID ANDERSON
Special/Order Compliance 2/7/2024 Corrections Issued DAVID ANDERSON
Final 2/14/2024 OK to Issue CofO DAVID ANDERSON
Service/Power Release 3/11/2024 Approved DAVID ANDERSON