24345 W VANOWEN ST 91307
Certificate Information: 24345 W VANOWEN ST 91307
- Application / Permit
- 23016-20000-11951
- Plan Check / Job No.
- B23VN04884
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan Convert Existing 1-Story Detached 2-Car Garage Type VB U Occupancy into New Accessory Dwelling Unit PER STATE LAW
- Permit Issued
- Issued on 8/17/2023
- Issuing Office
- Current Status
- CofO Issued on 1/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2023 | KHUONG TRUONG |
| Corrections Issued | 4/22/2023 | KHUONG TRUONG |
| Plan Check Approved | 8/16/2023 | KHUONG TRUONG |
| Issued | 8/17/2023 | APPLICANT |
| CofO in Progress | 12/19/2023 | TROY SANDERS |
| CofO Issued | 1/10/2024 | JOHN JANSON |
| Permit Finaled | 1/10/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 4/26/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 4/26/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 4/27/2023 | NIKKI ZULUETA |
| Construction near power lines | Cleared | 8/14/2023 | RIDWAN HARDY |
| Hold | Cleared | 9/20/2023 | MARIA VENDIVIL |
Contact Information
| Architect | Stockton,, Richard Kenneth; Lic. No.: NA35492 | , |
| Contractor | Build 4 You Inc; Lic. No.: 914440-B | , |
| Engineer | Van, Elden, Alexander Craig; Lic. No.: C71696 | 2415 FORDHAM DR COSTA MESA, CA 92626 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/21/2023 | Partial Approval | TROY SANDERS |
| Footing/Foundation/Slab | 8/24/2023 | Approved | MORRIS JACKSON |
| ELECTRICAL-Rough | 9/22/2023 | Approved | JEFFREY HARTLINE |
| HVAC-Rough | 9/22/2023 | Approved | JEFFREY HARTLINE |
| PLUMBING-Rough | 9/22/2023 | Approved | JEFFREY HARTLINE |
| Deputy Wood Construction | 9/29/2023 | Conditional Approval | TROY SANDERS |
| BUILDING-Rough-Frame | 10/2/2023 | Approved | TROY SANDERS |
| Green Building Rough | 10/2/2023 | Not Ready for Inspection | TROY SANDERS |
| Interior/Exterior Lathing | 10/2/2023 | Not Ready for Inspection | TROY SANDERS |
| Shower Pan | 10/2/2023 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 10/6/2023 | Approved | TROY SANDERS |
| Green Building Rough | 10/6/2023 | Approved | TROY SANDERS |
| Insulation | 10/6/2023 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 10/6/2023 | Partial Approval | TROY SANDERS |
| Drywall Nailing | 10/13/2023 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 10/13/2023 | Approved | JEFFREY HARTLINE |
| Sewer | 11/21/2023 | Approved | MORRIS JACKSON |
| Final | 12/13/2023 | Corrections Issued | JEFFREY HARTLINE |
| Green Building Final | 12/13/2023 | Approved | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 12/13/2023 | SGSOV Approved | JEFFREY HARTLINE |
| Smoke Detectors | 12/13/2023 | Approved | JEFFREY HARTLINE |
| Final | 12/18/2023 | OK to Issue CofO | TROY SANDERS |