2323 N ROSCOMARE ROAD 90077
Certificate Information: 2323 N ROSCOMARE ROAD 90077
- Application / Permit
- 23016-20000-11877
- Plan Check / Job No.
- B23VN04854
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (18) School - private
- Work Description
- CHANGE OF USE FROM GROCERY STORE TO PRE-SCHOOL, AND RESTRIPE PARKING LOT ALL WORK PER ENGINEERING NFPA 13 REQUIRED THROUGHOUT SEE COMMENTS NO CHANGE IN AREA/ HEIGHT OR FOOTPRINT
- Permit Issued
- Issued on 4/11/2024
- Issuing Office
- Valley
- Current Status
- Issued on 4/11/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/4/2023 | SEWADA ZADOORIAN MILAGARDI |
| Disabled Access Plans Picked Up | 5/11/2023 | APPLICANT |
| Green Plans Picked Up | 5/11/2023 | APPLICANT |
| Corrections Issued | 5/16/2023 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 5/17/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 5/22/2023 | APPLICANT |
| Applicant returned to address corrections | 12/11/2023 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 1/22/2024 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 2/15/2024 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 2/29/2024 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 3/14/2024 | SEWADA ZADOORAN MILAGARDI |
| No Progress | 3/14/2024 | SEWADA ZADOORAN MILAGARDI |
| Plan Check Approved | 3/14/2024 | SEWADA ZADOORAN MILAGARDI |
| Issued | 4/11/2024 | APPLICANT |
| TCO Issued (Expire Date: 05-06-2025) | 11/7/2024 | DAVID TSAU |
| TCO Issued (Expire Date: 10-28-2025) | 5/1/2025 | DAVID TSAU |
| TCO Issued (Expire Date: 04-14-2026) | 10/16/2025 | DAVID TSAU |
Permit Application Clearance Information
| Address approval | Cleared | 6/12/2023 | DINAH GARIN |
| Permit | Cleared | 6/12/2023 | DINAH GARIN |
| "Q" conditions | Cleared | 6/13/2023 | NATHAN ROMINE |
| "T" removal | Cleared | 6/13/2023 | NATHAN ROMINE |
| Tract Map conditions | Cleared | 6/13/2023 | NATHAN ROMINE |
| Grading Pre-Inspection | Cleared | 8/1/2023 | ROBERT HUGHES |
| Eng Process Fee Ord 176,300 | Cleared | 9/21/2023 | DINAH GARIN |
| Trees in Parkway | Cleared | 10/10/2023 | ADALBERTO VERA |
| DAS Clearance | Cleared | 10/23/2023 | SEWADA ZADOORAN MILAGARDI |
| Green Code | Cleared | 10/26/2023 | MICHAEL AYERS |
| Prkng lot landscape/Water mgmt | Cleared | 12/20/2023 | RUBEN VASQUEZ |
| Internal circulation | Cleared | 1/10/2024 | FREDDY GARCIA |
| GPI Written Notices | Cleared | 2/22/2024 | SEWADA ZADOORAN MILAGARDI |
| Fire Marshal Fire Life Safety | Cleared | 3/14/2024 | DOMINIQUE MEDINA |
Contact Information
| Architect | Tabencki-Dombrowa,, Janek M; Lic. No.: C23642 | P.O.BOX 193 TOPANGA, CA 90290 |
| Contractor | Timberline Construction Inc; Lic. No.: 732308-B | 7152 HAZARD AVE WESTMINSTER, CA 92683 |
| Engineer | Koma,, Shahram Javadi; Lic. No.: C69497 | 23241 VENTURA BLVD 300 WOODLAND HILLS, CA 91364 |
Inspector Information
| ROGELIO REYNA, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/15/2024 | Approved | GRANT WOODS |
| Pre-Inspection | 4/15/2024 | Approved | GRANT WOODS |
| Special/Order Compliance | 4/16/2024 | Corrections Issued | GRANT WOODS |
| Footing/Foundation/Slab | 4/17/2024 | Partial Approval | GRANT WOODS |
| Footing/Foundation/Slab | 4/18/2024 | Partial Approval | GRANT WOODS |
| Footing/Foundation/Slab | 4/22/2024 | Partial Approval | GRANT WOODS |
| Footing/Foundation/Slab | 5/3/2024 | Partial Approval | PAUL DAVIDSON |
| Deputy Other (see comments) | 5/15/2024 | Conditional Approval | RICARDO ROBLES |
| Deputy Steel/Welding | 5/15/2024 | Conditional Approval | RICARDO ROBLES |
| Deputy Wood Construction | 5/15/2024 | Partial Approval | ALAN NOVAK |
| Wood Frame | 5/17/2024 | Partial Approval | PAUL DAVIDSON |
| Deputy Wood Construction | 5/23/2024 | Approved | GRANT WOODS |
| Special/Order Compliance | 5/23/2024 | Approved | GRANT WOODS |
| Wood Frame | 5/29/2024 | Partial Approval | GRANT WOODS |
| Deputy Wood Construction | 6/6/2024 | Conditional Approval | GRANT WOODS |
| Deputy Drilled-In Anchors | 6/20/2024 | Conditional Approval | GRANT WOODS |
| Green Building Rough | 6/21/2024 | Not Ready for Inspection | GRANT WOODS |
| Verify Sprinkler Sign Off | 6/21/2024 | Not Ready for Inspection | GRANT WOODS |
| Wood Frame | 6/21/2024 | Partial Approval | GRANT WOODS |
| Excavation/Setback/Form/Re-Bar | 6/25/2024 | Not Ready for Inspection | GRANT WOODS |
| Footing/Foundation/Slab | 7/10/2024 | Partial Approval | GRANT WOODS |
| Deputy Reinf. Concrete | 7/22/2024 | Conditional Approval | GRANT WOODS |
| Light Gage Steel Frame | 7/23/2024 | Not Ready for Inspection | GRANT WOODS |
| Drywall Nailing | 8/6/2024 | Partial Approval | GRANT WOODS |
| Green Building Rough | 8/6/2024 | Not Ready for Inspection | GRANT WOODS |
| Verify Sprinkler Sign Off | 8/6/2024 | Partial Approval | GRANT WOODS |
| Wood Frame | 8/6/2024 | Not Ready for Inspection | GRANT WOODS |
| Deputy Wood Construction | 8/8/2024 | Conditional Approval | GRANT WOODS |
| Drywall Nailing | 8/12/2024 | Partial Approval | GRANT WOODS |
| Green Building Rough | 8/12/2024 | Partial Approval | GRANT WOODS |
| Special/Order Compliance | 8/26/2024 | Corrections Issued | GRANT WOODS |
| Interior/Exterior Lathing | 9/10/2024 | Partial Inspection | GRANT WOODS |
| Pre-Inspection | 9/20/2024 | Corrections Issued | GRANT WOODS |
| Special/Order Compliance | 4/8/2025 | Not Ready for Inspection | VASIL MIHALEV |
| Pre-Inspection | 7/24/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Special/Order Compliance | 9/30/2025 | Partial Inspection | VASIL MIHALEV |
| Special/Order Compliance | 3/18/2026 | Partial Inspection | ROGELIO REYNA |