14159-14161 W GAULT ST 91405

Certificate Information: 14159-14161 W GAULT ST 91405

Application / Permit
23016-20000-11484
Plan Check / Job No.
B23VN04729
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(E) GARAGE CONVERSION TO JR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND 65852.22, WORK PER WFPP
Permit Issued
Issued on 5/26/2023
Issuing Office
Current Status
CofO Issued on 5/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/13/2023 APPLICANT
Assigned to Plan Check Engineer 4/18/2023 JESSE ARELLANO
Corrections Issued 4/18/2023 JESSE ARELLANO
Plan Check Approved 5/25/2023 RAMA DABADGE
Building Plans Picked Up 5/25/2023 APPLICANT
Issued 5/26/2023 APPLICANT
CofO in Progress 5/3/2024 RYAN SALAZAR
Permit Finaled 5/15/2024 RUBEN SALAS
CofO Issued 5/15/2024 RUBEN SALAS
Permit Finaled 5/15/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/20/2023 LEE GUILBEAUX
Sewer availability Cleared 4/20/2023 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 4/24/2023 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/1/2023 Conditional Approval MISAEL ESPARZA
PLUMBING-Rough 9/1/2023 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 10/10/2023 Approved RYAN SALAZAR
PLUMBING-Rough 10/20/2023 Approved RYAN SALAZAR
BUILDING-Rough-Frame 10/30/2023 Approved RYAN SALAZAR
ELECTRICAL-Rough 10/30/2023 Approved RYAN SALAZAR
Green Building Rough 10/30/2023 Approved RYAN SALAZAR
HVAC-Rough 10/30/2023 Approved RYAN SALAZAR
PLUMBING-Final 10/30/2023 Approved RYAN SALAZAR
Insulation 11/9/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 11/9/2023 Partial Approval RYAN SALAZAR
Drywall Nailing 11/17/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 11/17/2023 Not Ready for Inspection RYAN SALAZAR
Shower Pan 11/17/2023 Approved RYAN SALAZAR
Sewer 12/11/2023 Approved RYAN SALAZAR
Underground Mechanical 1/2/2024 Approved RYAN SALAZAR
Pre-Inspection 3/26/2024 Partial Inspection RYAN SALAZAR
Final 4/26/2024 Partial Approval RYAN SALAZAR
Green Building Final 4/26/2024 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 4/26/2024 SGSOV Approved RYAN SALAZAR
Smoke Detectors 4/26/2024 Approved RYAN SALAZAR
Final 5/3/2024 OK to Issue CofO RYAN SALAZAR
Service/Power Release 5/9/2024 Approved RYAN SALAZAR