17433-17435 W LASSEN ST 91325

Certificate Information: 17433-17435 W LASSEN ST 91325

Application / Permit
23016-20000-11363
Plan Check / Job No.
B23VN04685
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan: CONVERT (E) ATTACHED GARAGE TO 423 SQ FT ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 5/24/2023
Issuing Office
Current Status
CofO Issued on 3/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/12/2023 APPLICANT
Assigned to Plan Check Engineer 4/18/2023 ALEC MOUSAKHANIAN
Corrections Issued 4/19/2023 ALEC MOUSAKHANIAN
Applicant returned to address corrections 5/3/2023 ALEC MOUSAKHANIAN
Applicant returned to address corrections 5/12/2023 HANS SANTIAGO
Plan Check Approved 5/23/2023 ANDREW SANTIAGO
Issued 5/24/2023 APPLICANT
CofO in Progress 12/15/2023 JAVIER RAMOS JR
Permit Finaled 3/6/2024 RUBEN SALAS
CofO Issued 3/6/2024 RUBEN SALAS
Permit Finaled 3/6/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/4/2023 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 5/4/2023 MEGAN GODINEZ
Sewer availability Cleared 5/4/2023 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 5/8/2023 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/12/2023 Partial Approval ROBERT GOLD
Footing/Foundation/Slab 9/18/2023 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 9/28/2023 Partial Inspection JAVIER RAMOS JR
BUILDING-Rough-Frame 10/10/2023 Partial Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 10/10/2023 Approved JAVIER RAMOS JR
HVAC-Rough 10/10/2023 Conditional Approval JAVIER RAMOS JR
PLUMBING-Rough 10/10/2023 Approved JAVIER RAMOS JR
Insulation 10/17/2023 Approved JAVIER RAMOS JR
Pre-Inspection 10/17/2023 Approved JAVIER RAMOS JR
Wood Frame 10/17/2023 Approved JAVIER RAMOS JR
Drywall Nailing 10/25/2023 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 10/25/2023 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 12/11/2023 Approved ROBERT GOLD
ELECTRICAL-Final 12/11/2023 Not Ready for Inspection ROBERT GOLD
Final 12/11/2023 Corrections Issued ROBERT GOLD
HVAC-Final 12/11/2023 Not Ready for Inspection ROBERT GOLD
PLUMBING-Final 12/11/2023 Not Ready for Inspection ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 12/11/2023 SGSOV Approved ROBERT GOLD
Service/Power Release 12/11/2023 Not Required ROBERT GOLD
Smoke Detectors 12/11/2023 Approved ROBERT GOLD
ELECTRICAL-Final 12/14/2023 Approved JAVIER RAMOS JR
Final 12/14/2023 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 12/14/2023 Approved JAVIER RAMOS JR
HVAC-Final 12/14/2023 Approved JAVIER RAMOS JR
PLUMBING-Final 12/14/2023 Approved JAVIER RAMOS JR