611 N OCCIDENTAL BLVD 1-10 90026
Certificate Information: 611 N OCCIDENTAL BLVD 1-10 90026
- Application / Permit
- 23016-20000-11278
- Plan Check / Job No.
- B23VN04660
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT IRREG SHAPED 20' X 20'-6" STORAGE ROOM TO ACCESSORY DWELLING UNIT (327 SQ FT) PER GCS 65852.2(e)(1)(C). ***SEE COMMENTS***
- Permit Issued
- Issued on 4/20/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/31/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/14/2023 | JEROME MAGAT PALMA |
| Corrections Issued | 4/15/2023 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 4/18/2023 | APPLICANT |
| Plan Check Approved | 4/19/2023 | OMAR GARNICA |
| Issued | 4/20/2023 | APPLICANT |
| CofO in Progress | 8/29/2023 | VAHE KELEDJIAN |
| CofO Issued | 8/31/2023 | WINSTON DUNNING |
| Permit Finaled | 8/31/2023 | WINSTON DUNNING |
Permit Application Clearance Information
| Address approval | Cleared | 4/17/2023 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 4/17/2023 | JEANIE LAM |
| Sewer availability | Cleared | 4/17/2023 | JEANIE LAM |
Contact Information
| Architect | Nigosian,, Michael Nickolas; Lic. No.: C35308 | 75-572 PAINTED DESERT DRIVE INDIAN WELLS, CA 92210 |
| Contractor | Derrich Company; Lic. No.: 931100-B | 11649 SUNSHINE TER STUDIO CITY, CA 91604 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Green Building Rough | 6/13/2023 | Approved | RONALD JIMENEZ |
| METHANE-Rough | 6/13/2023 | Approved | RONALD JIMENEZ |
| Wood Frame | 6/13/2023 | Approved | RONALD JIMENEZ |
| Insulation | 6/21/2023 | Approved | TIMOTHY POWELL |
| Drywall Nailing | 6/27/2023 | Approved | MARTIN TAVITIAN |
| Interior/Exterior Lathing | 6/27/2023 | Approved | MARTIN TAVITIAN |
| Final | 8/18/2023 | Partial Inspection | VAHE KELEDJIAN |
| Green Building Final | 8/18/2023 | Approved | VAHE KELEDJIAN |
| SGSOV-Seismic Gas S/O Valve | 8/18/2023 | SGSOV Not Ready | VAHE KELEDJIAN |
| Smoke Detectors | 8/18/2023 | Approved | VAHE KELEDJIAN |
| Final | 8/25/2023 | OK to Issue CofO | VAHE KELEDJIAN |
| SGSOV-Seismic Gas S/O Valve | 8/25/2023 | SGSOV Approved | VAHE KELEDJIAN |