6444 N SUNNYSLOPE AVE 91401
Certificate Information: 6444 N SUNNYSLOPE AVE 91401
- Application / Permit
- 23016-20000-11112
- Plan Check / Job No.
- B23VN04588
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 44' X 25' IRR.-SHAPE GARAGE/STORAGE TO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A). ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 4/28/2023
- Issuing Office
- Current Status
- CofO Issued on 1/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/13/2023 | JESSE ARELLANO |
| Corrections Issued | 4/15/2023 | JESSE ARELLANO |
| Building Plans Picked Up | 4/17/2023 | APPLICANT |
| Plan Check Approved | 4/28/2023 | GURUNATH NESARAJAH |
| Issued | 4/28/2023 | APPLICANT |
| CofO in Progress | 10/2/2023 | KIRK SANDERS |
| Permit Finaled | 1/17/2024 | RUBEN SALAS |
| CofO Issued | 1/17/2024 | RUBEN SALAS |
| Permit Finaled | 1/17/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/18/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 4/18/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 4/22/2023 | MARKOS PEREZ-BRAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/11/2023 | Conditional Approval | KIRK SANDERS |
| Excavation/Setback/Form/Re-Bar | 5/17/2023 | Approved | KIRK SANDERS |
| Footing/Foundation/Slab | 5/17/2023 | Approved | KIRK SANDERS |
| Underground Mechanical | 5/17/2023 | Partial Approval | KIRK SANDERS |
| BUILDING-Rough-Frame | 6/13/2023 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Rough | 6/13/2023 | Corrections Issued | KIRK SANDERS |
| Green Building Rough | 6/13/2023 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Rough | 6/13/2023 | Approved | KIRK SANDERS |
| PLUMBING-Rough | 6/13/2023 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 6/26/2023 | Approved | KIRK SANDERS |
| ELECTRICAL-Rough | 6/26/2023 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2023 | Partial Approval | KIRK SANDERS |
| Green Building Rough | 6/26/2023 | Approved | KIRK SANDERS |
| Insulation | 7/5/2023 | Not Ready for Inspection | JUAN VALENZUELA |
| Interior/Exterior Lathing | 7/5/2023 | Partial Approval | JUAN VALENZUELA |
| Shower Pan | 7/5/2023 | Approved | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2023 | Approved | ROBERT GOLD |
| Insulation | 7/11/2023 | Approved | ROBERT GOLD |
| Drywall Nailing | 7/18/2023 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 7/28/2023 | Approved | KIRK SANDERS |
| Underground Mechanical | 7/28/2023 | Corrections Issued | KIRK SANDERS |
| Underground Mechanical | 8/8/2023 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 9/18/2023 | Corrections Issued | KIRK SANDERS |
| Final | 9/18/2023 | Corrections Issued | KIRK SANDERS |
| Gas Test | 9/18/2023 | Approved | KIRK SANDERS |
| Green Building Final | 9/18/2023 | Approved | KIRK SANDERS |
| HVAC-Final | 9/18/2023 | Approved | KIRK SANDERS |
| PLUMBING-Final | 9/18/2023 | Corrections Issued | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 9/18/2023 | SGSOV Not Ready | KIRK SANDERS |
| Smoke Detectors | 9/18/2023 | Approved | KIRK SANDERS |
| Final | 9/29/2023 | OK to Issue CofO | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 9/29/2023 | SGSOV Approved | KIRK SANDERS |