6444 N SUNNYSLOPE AVE 91401

Certificate Information: 6444 N SUNNYSLOPE AVE 91401

Application / Permit
23016-20000-11112
Plan Check / Job No.
B23VN04588
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 44' X 25' IRR.-SHAPE GARAGE/STORAGE TO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A). ALL WORK DONE PER WFPP.
Permit Issued
Issued on 4/28/2023
Issuing Office
Current Status
CofO Issued on 1/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/11/2023 APPLICANT
Assigned to Plan Check Engineer 4/13/2023 JESSE ARELLANO
Corrections Issued 4/15/2023 JESSE ARELLANO
Building Plans Picked Up 4/17/2023 APPLICANT
Plan Check Approved 4/28/2023 GURUNATH NESARAJAH
Issued 4/28/2023 APPLICANT
CofO in Progress 10/2/2023 KIRK SANDERS
Permit Finaled 1/17/2024 RUBEN SALAS
CofO Issued 1/17/2024 RUBEN SALAS
Permit Finaled 1/17/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/18/2023 NIKKI ZULUETA
Sewer availability Cleared 4/18/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 4/22/2023 MARKOS PEREZ-BRAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/11/2023 Conditional Approval KIRK SANDERS
Excavation/Setback/Form/Re-Bar 5/17/2023 Approved KIRK SANDERS
Footing/Foundation/Slab 5/17/2023 Approved KIRK SANDERS
Underground Mechanical 5/17/2023 Partial Approval KIRK SANDERS
BUILDING-Rough-Frame 6/13/2023 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Rough 6/13/2023 Corrections Issued KIRK SANDERS
Green Building Rough 6/13/2023 Not Ready for Inspection KIRK SANDERS
HVAC-Rough 6/13/2023 Approved KIRK SANDERS
PLUMBING-Rough 6/13/2023 Approved KIRK SANDERS
BUILDING-Rough-Frame 6/26/2023 Approved KIRK SANDERS
ELECTRICAL-Rough 6/26/2023 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 6/26/2023 Partial Approval KIRK SANDERS
Green Building Rough 6/26/2023 Approved KIRK SANDERS
Insulation 7/5/2023 Not Ready for Inspection JUAN VALENZUELA
Interior/Exterior Lathing 7/5/2023 Partial Approval JUAN VALENZUELA
Shower Pan 7/5/2023 Approved JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 7/11/2023 Approved ROBERT GOLD
Insulation 7/11/2023 Approved ROBERT GOLD
Drywall Nailing 7/18/2023 Approved KIRK SANDERS
Interior/Exterior Lathing 7/28/2023 Approved KIRK SANDERS
Underground Mechanical 7/28/2023 Corrections Issued KIRK SANDERS
Underground Mechanical 8/8/2023 Approved KIRK SANDERS
ELECTRICAL-Final 9/18/2023 Corrections Issued KIRK SANDERS
Final 9/18/2023 Corrections Issued KIRK SANDERS
Gas Test 9/18/2023 Approved KIRK SANDERS
Green Building Final 9/18/2023 Approved KIRK SANDERS
HVAC-Final 9/18/2023 Approved KIRK SANDERS
PLUMBING-Final 9/18/2023 Corrections Issued KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 9/18/2023 SGSOV Not Ready KIRK SANDERS
Smoke Detectors 9/18/2023 Approved KIRK SANDERS
Final 9/29/2023 OK to Issue CofO KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 9/29/2023 SGSOV Approved KIRK SANDERS