9458-9460 N NAGLE AVE 91331
Certificate Information: 9458-9460 N NAGLE AVE 91331
- Application / Permit
- 23016-20000-11002
- Plan Check / Job No.
- B23VN04556
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan: CONVERT (E) 19' x 20' 2-CAR GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 6/14/2023
- Issuing Office
- Current Status
- CofO Issued on 1/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/17/2023 | PINANK PATEL |
| Corrections Issued | 4/17/2023 | PINANK PATEL |
| Plan Check Approved | 6/13/2023 | GURUNATH NESARAJAH |
| Issued | 6/14/2023 | APPLICANT |
| CofO in Progress | 12/28/2023 | GREGG CUMMINGS |
| Permit Finaled | 1/31/2024 | RUBEN SALAS |
| Permit Finaled | 1/31/2024 | RUBEN SALAS |
| CofO Issued | 1/31/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/19/2023 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 4/19/2023 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/2/2023 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/7/2023 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 8/7/2023 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 8/7/2023 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 8/7/2023 | Partial Approval | GREGG CUMMINGS |
| Sewer | 8/7/2023 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 8/25/2023 | Corrections Issued | RAUL OLAGI |
| HVAC-Rough | 8/25/2023 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 8/25/2023 | Corrections Issued | RAUL OLAGI |
| Special/Order Compliance | 8/25/2023 | Partial Approval | RAUL OLAGI |
| ELECTRICAL-Rough | 8/30/2023 | Approved | GREGG CUMMINGS |
| Green Building Rough | 8/30/2023 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 8/30/2023 | Approved | GREGG CUMMINGS |
| Insulation | 9/5/2023 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 9/21/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Drywall Nailing | 9/25/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 9/26/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Drywall Nailing | 9/26/2023 | Partial Approval | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 9/26/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 9/29/2023 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 9/29/2023 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 9/29/2023 | Approved | GREGG CUMMINGS |
| Final | 10/31/2023 | Corrections Issued | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 10/31/2023 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 10/31/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 12/18/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 12/18/2023 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 12/18/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 12/22/2023 | Corrections Issued | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 12/22/2023 | SGSOV Approved | GREGG CUMMINGS |
| Smoke Detectors | 12/22/2023 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 12/27/2023 | Approved | GREGG CUMMINGS |
| Final | 12/27/2023 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 12/27/2023 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 12/27/2023 | Approved | GREGG CUMMINGS |
| Service/Power Release | 12/27/2023 | Approved | GREGG CUMMINGS |