7860 N FERNCOLA AVE 91352
Certificate Information: 7860 N FERNCOLA AVE 91352
- Application / Permit
- 23016-20000-10933
- Plan Check / Job No.
- B23VN04542
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING 30'-0" X 20'-0" DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER PER GCS65852.2(e)(1)(A) - PER ENGINEER
- Permit Issued
- Issued on 5/8/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/13/2023 | JESSE ARELLANO |
| Corrections Issued | 4/16/2023 | JESSE ARELLANO |
| Building Plans Picked Up | 4/19/2023 | APPLICANT |
| Plan Check Approved | 5/4/2023 | DANIEL ABRAMYAN |
| Issued | 5/8/2023 | APPLICANT |
| CofO in Progress | 1/30/2024 | DAVID ANDERSON |
| Permit Finaled | 3/21/2024 | RUBEN SALAS |
| CofO Issued | 3/21/2024 | RUBEN SALAS |
| Permit Finaled | 3/21/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/24/2023 | SHAELYN ROWEN |
| Sewer availability | Cleared | 4/24/2023 | SHAELYN ROWEN |
| Eng Process Fee Ord 176,300 | Cleared | 4/27/2023 | SHAELYN ROWEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barragan,, Pedro; Lic. No.: C90531 | 329 N HUBBARD AVE SAN FERNANDO, CA 91340 |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/26/2023 | No Access for Inspection | DAVID ANDERSON |
| Pre-Inspection | 6/5/2023 | Approved | DAVID ANDERSON |
| Deputy Drilled-In Anchors | 8/3/2023 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 8/9/2023 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 9/29/2023 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Rough | 9/29/2023 | Approved | DAVID ANDERSON |
| Green Building Rough | 9/29/2023 | Approved | DAVID ANDERSON |
| HVAC-Rough | 9/29/2023 | Approved | DAVID ANDERSON |
| MERV13>=Rough | 9/29/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 9/29/2023 | Corrections Issued | DAVID ANDERSON |
| Sewer | 9/29/2023 | Approved | DAVID ANDERSON |
| Underground Mechanical | 9/29/2023 | Partial Approval | DAVID ANDERSON |
| BUILDING-Rough-Frame | 10/10/2023 | Partial Approval | DAVID ANDERSON |
| PLUMBING-Rough | 10/10/2023 | Approved | DAVID ANDERSON |
| Insulation | 10/24/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 10/24/2023 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 10/30/2023 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2023 | Approved | DAVID ANDERSON |
| Drywall Nailing | 11/14/2023 | Approved | DAVID ANDERSON |
| Final | 1/24/2024 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 1/24/2024 | Approved | DAVID ANDERSON |
| MERV13>=Final | 1/24/2024 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 1/24/2024 | SGSOV Not Ready | DAVID ANDERSON |
| Smoke Detectors | 1/24/2024 | Approved | DAVID ANDERSON |
| Final | 1/29/2024 | OK to Issue CofO | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 1/29/2024 | SGSOV Approved | DAVID ANDERSON |