7100 N FAIR AVE 91605
Certificate Information: 7100 N FAIR AVE 91605
- Application / Permit
- 23016-20000-10931
- Plan Check / Job No.
- B23VN04541
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (22) Warehouse
- Work Description
- ePLAN- ALTERATION TO WAREHOUSE. New tenant improvement of enlarge office area. Restripe portion of parking lot. Structural changes per engineer.
- Permit Issued
- Issued on 5/23/2023
- Issuing Office
- Current Status
- Permit Finaled on 2/20/2024
Permit Application Status History
| Submitted | 4/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/13/2023 | ARSALAN SHABESTARI |
| Corrections Issued | 4/16/2023 | ARSALAN SHABESTARI |
| Quality Review Completed | 4/21/2023 | GARO TELMI |
| Plan Check Approved | 5/23/2023 | ARSALAN SHABESTARI |
| Issued | 5/23/2023 | APPLICANT |
| Permit Finaled | 2/16/2024 | ROBERT DAVIS |
Permit Application Clearance Information
| DAS Clearance | Cleared | 5/12/2023 | Jesse Jimenez |
| Eng Process Fee Ord 176,300 | Cleared | 5/19/2023 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 5/19/2023 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Little Foot Construction Inc; Lic. No.: 800241-B | , |
| Engineer | Nguyen,, Thang Van; Lic. No.: NA79829 | , |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/12/2023 | Approved | ROBERT DAVIS |
| Pre-Inspection | 7/13/2023 | Not Ready for Inspection | BRIAN KELLY |
| Drywall Nailing | 7/14/2023 | Not Ready for Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 7/14/2023 | Not Ready for Inspection | JEFFREY FULTON |
| Drywall Nailing | 7/17/2023 | Partial Approval | ROBERT DAVIS |
| Insulation | 7/17/2023 | Approved | ROBERT DAVIS |
| Light Gage Steel Frame | 7/17/2023 | Approved | ROBERT DAVIS |
| Drywall Nailing | 7/20/2023 | Approved | ROBERT DAVIS |
| Wood Frame | 7/24/2023 | Approved | ROBERT DAVIS |
| T-Bar Ceiling | 8/11/2023 | Not Ready for Inspection | ANDREW DORSO |
| T-Bar Ceiling | 8/30/2023 | Approved | ROBERT DAVIS |
| Final | 2/16/2024 | Permit Finaled | ROBERT DAVIS |
| SGSOV-Seismic Gas S/O Valve | 2/16/2024 | SGSOV No Gas | ROBERT DAVIS |
| Smoke Detectors | 2/16/2024 | Approved | ROBERT DAVIS |