12978-12980 W CROWLEY ST 91331
Certificate Information: 12978-12980 W CROWLEY ST 91331
- Application / Permit
- 23016-20000-10774
- Plan Check / Job No.
- B23VN04505
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT EXISTING 20'-0" X 20'-0" ATTACHED GARAGE INTO JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND 65852.22 WITH 5'-9" X 5'-0" PORTION TO BE NEW LAUNDRY ROOM FOR THE ATTACHED SINGLE FAMILY DWELLING - PER WFPP
- Permit Issued
- Issued on 6/15/2023
- Issuing Office
- Current Status
- CofO Issued on 4/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/14/2023 | DANIEL ABRAMYAN |
| Corrections Issued | 4/17/2023 | DANIEL ABRAMYAN |
| Plan Check Approved | 6/15/2023 | DANIEL ABRAMYAN |
| Issued | 6/15/2023 | APPLICANT |
| CofO in Progress | 4/12/2024 | GREGG CUMMINGS |
| Permit Finaled | 4/24/2024 | RUBEN SALAS |
| CofO Issued | 4/24/2024 | RUBEN SALAS |
| Permit Finaled | 4/24/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/4/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 5/4/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 5/4/2023 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/24/2023 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 8/24/2023 | Partial Approval | GREGG CUMMINGS |
| Underground Mechanical | 8/24/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 11/15/2023 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 11/15/2023 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Rough | 11/15/2023 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 11/15/2023 | Corrections Issued | GREGG CUMMINGS |
| Sewer | 11/15/2023 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 11/29/2023 | Partial Approval | GREGG CUMMINGS |
| ELECTRICAL-Rough | 11/29/2023 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 11/29/2023 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 11/29/2023 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 12/15/2023 | Partial Approval | GREGG CUMMINGS |
| Shower Pan | 12/15/2023 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 1/12/2024 | Approved | GREGG CUMMINGS |
| Insulation | 1/12/2024 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 1/25/2024 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 1/25/2024 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 4/2/2024 | Approved | GREGG CUMMINGS |
| Final | 4/2/2024 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Final | 4/2/2024 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 4/2/2024 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 4/2/2024 | SGSOV Approved | GREGG CUMMINGS |
| Smoke Detectors | 4/2/2024 | Approved | GREGG CUMMINGS |
| Final | 4/10/2024 | OK to Issue CofO | GREGG CUMMINGS |
| Service/Power Release | 4/10/2024 | Approved | GREGG CUMMINGS |