7907-7911 N VANTAGE AVE 91605
Certificate Information: 7907-7911 N VANTAGE AVE 91605
- Application / Permit
- 23016-20000-10555
- Plan Check / Job No.
- B23VN04423
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT 25'-2" X 18'-3" (417 SQ. FT.) PORTION OF (E) SFD TO JUNIOR ACCESSORY DWELLING UNIT GCS 65852.2(e)(1)(A) and 65852.22. ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 5/23/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/7/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/15/2023 | ARTIN ZARUKIAN |
| Corrections Issued | 4/15/2023 | ARTIN ZARUKIAN |
| Applicant returned to address corrections | 5/8/2023 | LUISANGEL VALENZUELA |
| Plan Check Approved | 5/23/2023 | HAYATO TSUCHIYA |
| Issued | 5/23/2023 | APPLICANT |
| CofO in Progress | 1/29/2024 | MATTHEW NELSON |
| Permit Finaled | 1/31/2024 | RUBEN SALAS |
| CofO Issued | 1/31/2024 | RUBEN SALAS |
| Permit Finaled | 1/31/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/19/2023 | MEGAN GODINEZ |
| Sewer availability | Cleared | 4/19/2023 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/26/2023 | MEGAN GODINEZ |
Contact Information
| Contractor | Mahtesyan Narek M; Lic. No.: 1025021-B | 515 N KENWOOD ST APT 302 GLENDALE, CA 91206 |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 7/24/2023 | Approved | MATTHEW NELSON |
| HVAC-Rough | 7/24/2023 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Rough | 7/24/2023 | Approved | MATTHEW NELSON |
| Sewer | 7/24/2023 | Approved | MATTHEW NELSON |
| Wood Frame | 7/24/2023 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 7/27/2023 | Approved | MATTHEW NELSON |
| HVAC-Rough | 7/27/2023 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 8/11/2023 | Approved | MATTHEW NELSON |
| Shower Pan | 8/11/2023 | Approved | MATTHEW NELSON |
| Insulation | 8/16/2023 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 9/5/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 9/5/2023 | Approved | RYAN SALAZAR |
| Final | 1/25/2024 | OK to Issue CofO | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 1/25/2024 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 1/25/2024 | Approved | MATTHEW NELSON |