5940 N VARIEL AVE 91367
Certificate Information: 5940 N VARIEL AVE 91367
- Application / Permit
- 23016-20000-10292
- Plan Check / Job No.
- B23VN04317
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (6) Church
- Work Description
- ePLAN- CHANGE OF USE AND OCCUPANCY FROM (e) OFFICE TO CHURCH AND SCHOOL. Interior TI only. Change of Occupancy from B Office to A-3 Assembly - Prayer Hall. Provide new non-bearing partition walls. Provide new doors and frames. Provide new suspended T-Bar ceiling and acoustic tiles. Provide new sinks, toilets & urinals. ADD NEW BEAMS AND PAD FOUNDATION. NEW ROOFTOP EQUIPMENT.
- Permit Issued
- Issued on 8/30/2023
- Issuing Office
- Current Status
- CofO Issued on 8/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/13/2023 | QUAN NGHIEM |
| Corrections Issued | 4/26/2023 | QUAN NGHIEM |
| Quality Review Completed | 5/1/2023 | CHAD DOI |
| Applicant returned to address corrections | 6/20/2023 | QUAN NGHIEM |
| Applicant returned to address corrections | 8/25/2023 | QUAN NGHIEM |
| Plan Check Approved | 8/29/2023 | QUAN NGHIEM |
| Issued | 8/30/2023 | APPLICANT |
| TCO Issued (Expire Date: 10-14-2024) | 4/17/2024 | JEFFREY DURAN |
| TCO Issued (Expire Date: 03-17-2025) | 9/18/2024 | JEFFREY DURAN |
| TCO Issued (Expire Date: 09-09-2025) | 3/13/2025 | JEFFREY DURAN |
| CofO in Progress | 8/18/2025 | BRIAN KELLY |
| Permit Finaled | 8/19/2025 | JEFFREY DURAN |
| CofO Issued | 8/19/2025 | JEFFREY DURAN |
| Permit Finaled | 8/19/2025 | JEFFREY DURAN |
Permit Application Clearance Information
| Green Code | Cleared | 4/18/2023 | MICHAEL AYERS |
| DAS Clearance | Cleared | 5/18/2023 | Ricardo Ramirez Solis |
| Sewer availability | Cleared | 5/22/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 5/24/2023 | DAGOVERTO GUERRERO |
| Fire Marshal Fire Life Safety | Cleared | 6/26/2023 | MENOA AGHAJANI |
| Specific Plan | Cleared | 8/23/2023 | NATHAN ROMINE |
Contact Information
| Architect | Dong,, Heney; Lic. No.: NA9770 | , |
| Contractor | Build Solutions; Lic. No.: 1047137-B | 1901 AVENUE OF THE STARS SUITE 200 LOS ANGELES, CA 90067 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/9/2023 | Corrections Issued | BRIAN KELLY |
| Deputy Drilled-In Anchors | 11/15/2023 | Approved | DEANDRE HOFFMAN |
| Excavation/Setback/Form/Re-Bar | 11/15/2023 | Partial Approval | DEANDRE HOFFMAN |
| Wood Frame | 11/15/2023 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Deputy Reinf. Concrete | 11/16/2023 | Conditional Approval | BRIAN KELLY |
| Footing/Foundation/Slab | 11/16/2023 | Not Ready for Inspection | BRIAN KELLY |
| T-Bar Ceiling | 11/17/2023 | Partial Inspection | BRIAN KELLY |
| Drywall Nailing | 11/21/2023 | Partial Inspection | BRIAN KELLY |
| Insulation | 12/19/2023 | Not Ready for Inspection | STEVEN LEVITT |
| Light Gage Steel Frame | 12/19/2023 | Partial Inspection | STEVEN LEVITT |
| Light Gage Steel Frame | 12/27/2023 | Partial Approval | BRIAN KELLY |
| Drywall Nailing | 12/29/2023 | Partial Approval | BRIAN KELLY |
| Insulation | 12/29/2023 | Approved | BRIAN KELLY |
| Drywall Nailing | 1/4/2024 | Partial Approval | BRIAN KELLY |
| Drywall Nailing | 1/9/2024 | Partial Approval | BRIAN KELLY |
| Pre-Inspection | 1/22/2024 | Partial Inspection | BRIAN KELLY |
| Special/Order Compliance | 1/22/2024 | Partial Inspection | MELVIN GIRTON |
| Pre-Inspection | 1/24/2024 | Partial Inspection | BRIAN KELLY |
| T-Bar Ceiling | 2/27/2024 | Partial Inspection | BRIAN KELLY |
| Grading Pre-Inspection | 2/28/2024 | Partial Inspection | BRIAN KELLY |
| Final | 3/28/2024 | Not Ready for Inspection | BRIAN KELLY |
| Green Building Final | 3/28/2024 | Not Ready for Inspection | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 3/28/2024 | SGSOV Not Ready | BRIAN KELLY |
| Smoke Detectors | 3/28/2024 | Not Ready for Inspection | BRIAN KELLY |
| Final | 4/3/2024 | No Access for Inspection | BRIAN KELLY |
| Green Building Final | 4/3/2024 | No Access for Inspection | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 4/3/2024 | SGSOV Not Ready | BRIAN KELLY |
| Smoke Detectors | 4/3/2024 | No Access for Inspection | BRIAN KELLY |
| Final | 4/5/2024 | OK to Issue CofO | BRIAN KELLY |
| Green Building Final | 4/5/2024 | Approved | BRIAN KELLY |
| Green Building Rough | 4/5/2024 | Approved | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 4/5/2024 | SGSOV Approved | BRIAN KELLY |
| Smoke Detectors | 4/5/2024 | Approved | BRIAN KELLY |
| Special/Order Compliance | 9/17/2024 | Partial Inspection | BRIAN KELLY |
| Special/Order Compliance | 2/19/2025 | Partial Inspection | BRIAN KELLY |
| Special/Order Compliance | 8/12/2025 | Partial Inspection | BRIAN KELLY |
| Final | 8/14/2025 | Partial Approval | BRIAN KELLY |
| Smoke Detectors | 8/14/2025 | Approved | BRIAN KELLY |