6655 1/2 N TROOST AVE 91606

Certificate Information: 6655 1/2 N TROOST AVE 91606

Application / Permit
23016-20000-10032
Plan Check / Job No.
B23VN04230
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 9/1/2023
Issuing Office
Valley
Current Status
CofO Issued on 3/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/4/2023 APPLICANT
Assigned to Plan Check Engineer 4/7/2023 JEROME MAGAT PALMA
Corrections Issued 4/7/2023 JEROME MAGAT PALMA
Building Plans Picked Up 4/12/2023 APPLICANT
Applicant returned to address corrections 4/18/2023 ALEC MOUSAKHANIAN
Plan Check Approved 7/28/2023 ISIS ARGUETA
Issued 9/1/2023 APPLICANT
CofO in Progress 1/28/2025 ROBERTO PALACIOS-LOPEZ
Permit Finaled 3/6/2025 RUBEN SALAS
CofO Issued 3/6/2025 RUBEN SALAS
Permit Finaled 3/6/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/14/2023 COLIN LOREDO
Sewer availability Cleared 4/14/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 4/18/2023 COLIN LOREDO
Construction near power lines Cleared 7/22/2023 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/25/2024 Approved JENNIFER RABUCHIN
Sewer 6/6/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Underground Mechanical 6/6/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Deputy Drilled-In Anchors 6/7/2024 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 6/7/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 6/7/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Sewer 6/7/2024 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 7/26/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 7/26/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 7/26/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 7/26/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
HVAC-Rough 7/26/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 7/26/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Shower Pan 7/26/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 8/9/2024 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 8/9/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 8/9/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Green Building Rough 8/9/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
HVAC-Rough 8/9/2024 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 8/9/2024 Approved ROBERTO PALACIOS-LOPEZ
Shower Pan 8/9/2024 Approved ROBERTO PALACIOS-LOPEZ
Wood Frame 8/9/2024 Approved ROBERTO PALACIOS-LOPEZ
Insulation 8/26/2024 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 8/26/2024 Approved MICHAEL CORTEZ
Drywall Nailing 9/3/2024 Approved JOSE AVILA
Interior/Exterior Lathing 9/10/2024 Partial Approval JOSE AVILA
BUILDING-Rough-Frame 12/18/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 12/18/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Gas Test 12/18/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 12/18/2024 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 12/18/2024 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Final 12/18/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 12/18/2024 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 12/18/2024 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Smoke Detectors 12/18/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 12/30/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 12/30/2024 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Final 12/30/2024 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 12/30/2024 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 12/30/2024 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Smoke Detectors 12/30/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 1/28/2025 OK to Issue CofO ROBERTO PALACIOS-LOPEZ