17422-17424 W ROSCOE BLVD 91325

Certificate Information: 17422-17424 W ROSCOE BLVD 91325

Application / Permit
23016-20000-09474
Plan Check / Job No.
B23VN04025
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT 13'-2" X 35'-2" (492 SF) PORTION OF (E) SFD TO JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND 65852.22. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 4/29/2024
Issuing Office
Valley
Current Status
CofO Issued on 10/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/30/2023 APPLICANT
Assigned to Plan Check Engineer 4/13/2023 RAPHAEL ROSAS
Corrections Issued 4/18/2023 RAPHAEL ROSAS
Quality Review Completed 4/20/2023 STEVEN KIM
Building Plans Picked Up 4/21/2023 APPLICANT
Applicant returned to address corrections 1/22/2024 RAPHAEL ROSAS
Plan Check Approved 2/5/2024 RAPHAEL ROSAS
Issued 4/29/2024 APPLICANT
CofO in Progress 10/21/2024 RAUL OLAGI
CofO Issued 10/22/2024 DANIEL ORRANTE
Permit Finaled 10/22/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 4/25/2023 NIKKI ZULUETA
Sewer availability Cleared 4/27/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 11/7/2023 BRYAN GODINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/6/2024 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 5/13/2024 Approved RAUL OLAGI
PLUMBING-Rough 5/13/2024 Partial Approval RAUL OLAGI
BUILDING-Rough-Frame 5/17/2024 Approved RAUL OLAGI
Insulation 5/17/2024 Approved RAUL OLAGI
PLUMBING-Rough 5/17/2024 Approved RAUL OLAGI
Drywall Nailing 5/20/2024 Approved RAUL OLAGI
ELECTRICAL-Final 5/29/2024 Approved RAUL OLAGI
Final 5/29/2024 Corrections Issued RAUL OLAGI
HVAC-Final 5/29/2024 Corrections Issued RAUL OLAGI
PLUMBING-Final 5/29/2024 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 5/29/2024 SGSOV Approved RAUL OLAGI
Smoke Detectors 5/29/2024 Approved RAUL OLAGI
HVAC-Final 6/27/2024 Corrections Issued RAUL OLAGI
Final 7/1/2024 Corrections Issued RAUL OLAGI
HVAC-Final 7/1/2024 Corrections Issued RAUL OLAGI
Final 7/12/2024 No Access for Inspection RAUL OLAGI
HVAC-Final 7/12/2024 No Access for Inspection RAUL OLAGI
Final 9/19/2024 Not Ready for Inspection RAUL OLAGI
Final 10/21/2024 OK to Issue CofO RAUL OLAGI