9959-9961 N WISNER AVE 91345
Certificate Information: 9959-9961 N WISNER AVE 91345
- Application / Permit
- 23016-20000-09293
- Plan Check / Job No.
- B23VN03954
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Junior Accessory Dwelling Unit
- Work Description
- eplan Existing 334.1 SF Garage Conversion to New same size 334.1 SF JADU per GCS 65852.2(e)(1)(A) and 65852.22
- Permit Issued
- Issued on 6/23/2023
- Issuing Office
- Current Status
- CofO Issued on 4/22/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/29/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/4/2023 | AMY GUEVARRA |
| Corrections Issued | 4/6/2023 | AMY GUEVARRA |
| Applicant returned to address corrections | 5/5/2023 | JESSE ARELLANO |
| Plan Check Approved | 6/13/2023 | JOHNPAUL ISIP |
| Issued | 6/23/2023 | APPLICANT |
| CofO in Progress | 4/8/2025 | JENNIFER RABUCHIN |
| Permit Finaled | 4/22/2025 | RUBEN SALAS |
| CofO Issued | 4/22/2025 | RUBEN SALAS |
| Permit Finaled | 4/22/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/11/2023 | CARLOS AGUILERA |
| Address approval | Cleared | 5/1/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 5/1/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 5/2/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/10/2023 | Not Ready for Inspection | DAVID MATSON |
| PLUMBING-Rough | 8/10/2023 | Not Ready for Inspection | DAVID MATSON |
| Deputy Drilled-In Anchors | 8/16/2023 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 8/16/2023 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 8/30/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 8/30/2023 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 9/6/2023 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 9/6/2023 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 9/18/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 9/18/2023 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 9/18/2023 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 9/28/2023 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2023 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 10/2/2023 | Approved | MICHEL ABAJAN |
| Insulation | 10/10/2023 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/11/2023 | Off-Hour Fees Due | |
| Drywall Nailing | 10/30/2023 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 8/15/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 8/15/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 8/15/2024 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 8/15/2024 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 8/15/2024 | Approved | JENNIFER RABUCHIN |
| Final | 10/11/2024 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 4/8/2025 | Approved | JENNIFER RABUCHIN |
| Final | 4/8/2025 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 4/8/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 4/8/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 4/8/2025 | Approved | JENNIFER RABUCHIN |