9238-9240 N PETIT AVE 91343
Certificate Information: 9238-9240 N PETIT AVE 91343
- Application / Permit
- 23016-20000-08942
- Plan Check / Job No.
- B23VN03813
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE INTO A ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 5/8/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/3/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2023 | SERGIO MUNIZ |
| Corrections Issued | 4/2/2023 | SERGIO MUNIZ |
| Building Plans Picked Up | 4/12/2023 | APPLICANT |
| Plan Check Approved | 4/25/2023 | PINANK PATEL |
| Issued | 5/8/2023 | APPLICANT |
| CofO in Progress | 1/22/2026 | GAREN HAYRAPETYAN |
| Permit Finaled | 2/3/2026 | RUBEN SALAS |
| CofO Issued | 2/3/2026 | RUBEN SALAS |
| Permit Finaled | 2/3/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/14/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 4/14/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 4/19/2023 | COLIN LOREDO |
| Grading Pre-Inspection | Cleared | 4/25/2023 | MICHAEL TEMPLE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/8/2023 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 5/30/2024 | Corrections Issued | RAUL OLAGI |
| Underground Mechanical | 6/3/2024 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 7/3/2024 | Partial Approval | RAUL OLAGI |
| Deputy Drilled-In Anchors | 10/4/2024 | Conditional Approval | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 10/8/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 10/8/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Excavation/Setback/Form/Re-Bar | 10/11/2024 | Partial Inspection | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 10/11/2024 | Partial Inspection | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 10/16/2024 | Approved | GAREN HAYRAPETYAN |
| Insulation | 10/22/2024 | Corrections Issued | GAREN HAYRAPETYAN |
| Insulation | 10/30/2024 | Partial Approval | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/25/2024 | Approved | GAREN HAYRAPETYAN |
| Rough-Elec/Plmb/HVAC | 3/24/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Sewer | 3/24/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Wood Frame | 3/24/2025 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 3/28/2025 | Approved | GAREN HAYRAPETYAN |
| HVAC-Rough | 3/28/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Wood Frame | 3/28/2025 | Approved | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 5/7/2025 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Rough | 5/7/2025 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Rough | 5/7/2025 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 5/7/2025 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 6/4/2025 | Approved | GAREN HAYRAPETYAN |
| Green Building Rough | 6/4/2025 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 6/4/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Insulation | 6/13/2025 | Approved | MICHAEL CORTEZ |
| Underground Mechanical | 6/13/2025 | Partial Approval | MICHAEL CORTEZ |
| Drywall Nailing | 7/9/2025 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 7/9/2025 | Approved | MICHAEL CORTEZ |
| Shower Pan | 7/16/2025 | Approved | JAVIER RAMOS JR |
| Final | 12/26/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Green Building Final | 12/26/2025 | Corrections Issued | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 12/26/2025 | SGSOV Approved | WAYNE REGESTER |
| Smoke Detectors | 12/26/2025 | Approved | WAYNE REGESTER |
| Final | 1/22/2026 | OK to Issue CofO | GAREN HAYRAPETYAN |
| Green Building Final | 1/22/2026 | Approved | GAREN HAYRAPETYAN |