10304 W ADDISON ST 91601

Certificate Information: 10304 W ADDISON ST 91601

Application / Permit
23016-20000-08915
Plan Check / Job No.
B23VN03805
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EXISTING DETACHED 2 CAR GARAGE AND REC ROOM TO BE CONVERTED TO 812 SQFT ADU
Permit Issued
Issued on 9/8/2023
Issuing Office
Valley
Current Status
CofO Issued on 4/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/28/2023 APPLICANT
Assigned to Plan Check Engineer 3/31/2023 SERGIO MUNIZ
Corrections Issued 4/3/2023 SERGIO MUNIZ
Building Plans Picked Up 4/5/2023 APPLICANT
Plan Check Approved 4/25/2023 HAYATO TSUCHIYA
Issued 9/8/2023 APPLICANT
CofO in Progress 3/11/2024 JOHN HAYES
Permit Finaled 4/3/2024 DANIEL ORRANTE
CofO Issued 4/3/2024 DANIEL ORRANTE
Permit Finaled 4/3/2024 DANIEL ORRANTE

Permit Application Clearance Information

Construction near power lines Cleared 4/6/2023 WALTER RAMIREZ
Address approval Cleared 4/13/2023 CARLOS AGUILERA
Sewer availability Cleared 4/13/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 4/24/2023 CARLOS AGUILERA

Contact Information

Contractor J P General Building Inc; Lic. No.: 762764-B 10366 HADDON AVE      PACOIMA, CA 91331
Engineer Reith,, David Lee; Lic. No.: C72122 1319 FEATHER AVE      THOUSAND OAKS, CA 91360

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/12/2023 Conditional Approval JOHN HAYES
ELECTRICAL-Rough 10/18/2023 Not Ready for Inspection JOHN HAYES
Excavation/Setback/Form/Re-Bar 10/18/2023 Corrections Issued JOHN HAYES
Underground Mechanical 10/18/2023 Approved JOHN HAYES
Deputy Drilled-In Anchors 10/19/2023 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 10/23/2023 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/7/2023 Partial Approval JOHN HAYES
Deputy Wood Construction 11/7/2023 Approved JOHN HAYES
ELECTRICAL-Rough 11/7/2023 Approved JOHN HAYES
Green Building Rough 11/7/2023 Not Ready for Inspection JOHN HAYES
HVAC-Rough 11/7/2023 Corrections Issued JOHN HAYES
PLUMBING-Rough 11/7/2023 Approved JOHN HAYES
BUILDING-Rough-Frame 11/16/2023 Approved JOHN HAYES
Green Building Rough 11/16/2023 Approved JOHN HAYES
Interior/Exterior Lathing 11/16/2023 Partial Approval JOHN HAYES
Rough-Elec/Plmb/HVAC 11/16/2023 Approved JOHN HAYES
Shower Pan 11/16/2023 Approved JOHN HAYES
Insulation 11/20/2023 Approved DAVID MATSON
Drywall Nailing 11/28/2023 Approved JOHN HAYES
Final 2/9/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Final 2/9/2024 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 2/9/2024 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 2/9/2024 Approved JENNIFER RABUCHIN
Final 2/15/2024 Not Ready for Inspection CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 2/15/2024 SGSOV Not Ready CRAIG DAVIS
Final 2/26/2024 OK to Issue CofO JOHN HAYES
SGSOV-Seismic Gas S/O Valve 2/26/2024 SGSOV Approved JOHN HAYES