9140 N SANDUSKY AVE 91331
Certificate Information: 9140 N SANDUSKY AVE 91331
- Application / Permit
- 23016-20000-08584
- Plan Check / Job No.
- B23VN03690
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 18'-0" X 8'-2" ADDITION TO (E) DETACHED GARAGE AND CONVERT INTO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d).WORK DONE PER WFPP. "COMPLY WITH DEPARTMENT ORDER effective date 01/19/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 11/22/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/23/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/29/2023 | ARTIN ZARUKIAN |
| Corrections Issued | 3/30/2023 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 4/6/2023 | APPLICANT |
| Applicant returned to address corrections | 10/19/2023 | ANGELICA DAVE |
| Plan Check Approved | 11/2/2023 | ROSENDO MEDINA |
| Issued | 11/22/2023 | APPLICANT |
| Permit Finaled | 6/2/2025 | DAVID JAMES |
| CofO Issued | 6/2/2025 | DAVID JAMES |
| Permit Finaled | 6/2/2025 | DAVID JAMES |
Permit Application Clearance Information
| Address approval | Cleared | 4/19/2023 | SHAELYN ROWEN |
| Roof/Waste drainage to street | Cleared | 4/19/2023 | SHAELYN ROWEN |
| Construction near power lines | Cleared | 9/23/2023 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 11/18/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 11/18/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIO CUEVAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/28/2024 | Approved | LEO MILBAUER |
| BUILDING-Rough-Frame | 9/9/2024 | Partial Inspection | LEO MILBAUER |
| ELECTRICAL-Rough | 9/9/2024 | Approved | LEO MILBAUER |
| Green Building Rough | 9/9/2024 | Not Ready for Inspection | LEO MILBAUER |
| HVAC-Rough | 9/9/2024 | Partial Inspection | LEO MILBAUER |
| PLUMBING-Rough | 9/9/2024 | Approved | LEO MILBAUER |
| Sewer | 9/9/2024 | Approved | LEO MILBAUER |
| BUILDING-Rough-Frame | 10/9/2024 | Approved | LEO MILBAUER |
| Green Building Rough | 10/9/2024 | Approved | LEO MILBAUER |
| Insulation | 10/9/2024 | Approved | LEO MILBAUER |
| Interior/Exterior Lathing | 10/9/2024 | Approved | LEO MILBAUER |
| Shower Pan | 10/9/2024 | Approved | LEO MILBAUER |
| Drywall Nailing | 10/16/2024 | Approved | LEO MILBAUER |
| Final | 2/3/2025 | Not Ready for Inspection | LEO MILBAUER |
| Footing/Foundation/Slab | 2/3/2025 | Approved | LEO MILBAUER |
| Green Building Final | 2/3/2025 | Approved | LEO MILBAUER |
| SGSOV-Seismic Gas S/O Valve | 2/3/2025 | SGSOV Not Ready | LEO MILBAUER |
| Smoke Detectors | 2/3/2025 | Approved | LEO MILBAUER |
| Final | 3/24/2025 | Conditional Approval | LEO MILBAUER |
| SGSOV-Seismic Gas S/O Valve | 3/24/2025 | SGSOV Approved | LEO MILBAUER |