4957 N DENNY AVE 91601

Certificate Information: 4957 N DENNY AVE 91601

Application / Permit
23016-20000-08529
Plan Check / Job No.
B23VN03659
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Add and convert (E) garage into one story detached ADU perLAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 4/13/2023
Issuing Office
Valley
Current Status
CofO Issued on 6/9/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/23/2023 APPLICANT
Assigned to Plan Check Engineer 3/29/2023 SERGIO MUNIZ
Corrections Issued 3/30/2023 SERGIO MUNIZ
Building Plans Picked Up 4/5/2023 APPLICANT
Plan Check Approved 4/13/2023 RAMA DABADGE
Issued 4/13/2023 APPLICANT
CofO in Progress 5/31/2023 ROBERT GOLD
CofO Issued 6/9/2023 MICHAEL SMITH
Permit Finaled 6/9/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 4/6/2023 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 4/6/2023 ROMAN GUTIERREZ
Roof/Waste drainage to street Cleared 4/6/2023 ROMAN GUTIERREZ
Sewer availability Cleared 4/6/2023 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Dike,, Nnadozie; Lic. No.: C87565 PO BOX 1108      GLENDALE, CA 91209

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 4/18/2023 Not Ready for Inspection JOHN HAYES
Final 4/18/2023 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 4/18/2023 Not Ready for Inspection JOHN HAYES
Green Building Final 4/18/2023 Not Ready for Inspection JOHN HAYES
Green Building Rough 4/18/2023 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 4/18/2023 SGSOV Not Ready JOHN HAYES
Smoke Detectors 4/18/2023 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Rough 5/4/2023 Corrections Issued ROBERT GOLD
HVAC-Rough 5/4/2023 Partial Approval ROBERT GOLD
PLUMBING-Rough 5/4/2023 Partial Approval ROBERT GOLD
BUILDING-Rough-Frame 5/16/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 5/16/2023 Approved JENNIFER RABUCHIN
Final 5/16/2023 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 5/16/2023 Approved JENNIFER RABUCHIN
Green Building Final 5/16/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 5/16/2023 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 5/16/2023 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 5/16/2023 Approved JENNIFER RABUCHIN
HVAC-Final 5/22/2023 Approved JOHN HAYES
Final 5/30/2023 OK to Issue CofO JENNIFER RABUCHIN