7608 1/2 S TRUXTON AVE 90045
Certificate Information: 7608 1/2 S TRUXTON AVE 90045
- Application / Permit
- 23016-20000-08155
- Plan Check / Job No.
- B23VN03525
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO (N) 361 SF ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 4/26/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/23/2023 | JEROME MAGAT PALMA |
| Corrections Issued | 3/25/2023 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 3/29/2023 | APPLICANT |
| Issued | 4/26/2023 | APPLICANT |
| CofO in Progress | 8/25/2023 | BOBBY KEY |
| Permit Finaled | 9/6/2023 | DANIEL ORRANTE |
| CofO Issued | 9/6/2023 | DANIEL ORRANTE |
| Permit Finaled | 9/6/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 4/3/2023 | DINAH GARIN |
| Sewer availability | Cleared | 4/3/2023 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 4/4/2023 | DINAH GARIN |
| Specific Plan | Cleared | 4/18/2023 | JOSHUA JONES |
| Grading Pre-Inspection | Cleared | 4/20/2023 | KIRK LINKLATER |
Contact Information
| Contractor | Nittay Inc; Lic. No.: 1033506-B | 17941 VENTURA BLVD #204 ENCINO, CA 91316 |
| Engineer | Rahman,, Moksudur; Lic. No.: C69263 | 14616 MCKENDREE AVE CHINO, CA 91708 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2023 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 5/5/2023 | Corrections Issued | BOBBY KEY |
| Deputy Drilled-In Anchors | 5/10/2023 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 5/10/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 5/30/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 5/30/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 5/30/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 6/1/2023 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2023 | Not Ready for Inspection | BOBBY KEY |
| Rough-Elec/Plmb/HVAC | 6/2/2023 | Approved | BOBBY KEY |
| Insulation | 6/5/2023 | Corrections Issued | BOBBY KEY |
| Insulation | 6/9/2023 | Corrections Issued | BOBBY KEY |
| Interior/Exterior Lathing | 6/9/2023 | Partial Approval | BOBBY KEY |
| Insulation | 6/12/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Insulation | 6/13/2023 | Approved | BOBBY KEY |
| Special/Order Compliance | 6/13/2023 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2023 | Not Ready for Inspection | BOBBY KEY |
| Sewer | 6/15/2023 | Not Ready for Inspection | BOBBY KEY |
| Underground Mechanical | 6/15/2023 | Not Ready for Inspection | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2023 | Not Ready for Inspection | BOBBY KEY |
| Sewer | 6/16/2023 | Approved | BOBBY KEY |
| Underground Mechanical | 6/16/2023 | Partial Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 6/26/2023 | Approved | BOBBY KEY |
| Green Building Rough | 6/26/2023 | Approved | BOBBY KEY |
| Verify Sprinkler Sign Off | 6/26/2023 | Approved | BOBBY KEY |
| Shower Pan | 6/27/2023 | Approved | BOBBY KEY |
| Drywall Nailing | 6/29/2023 | Conditional Approval | BOBBY KEY |
| Interior/Exterior Lathing | 7/3/2023 | Approved | BOBBY KEY |
| Special/Order Compliance | 7/31/2023 | Partial Inspection | BOBBY KEY |
| Special/Order Compliance | 8/2/2023 | Partial Inspection | BOBBY KEY |
| ELECTRICAL-Final | 8/22/2023 | Approved | BOBBY KEY |
| Final | 8/22/2023 | Corrections Issued | BOBBY KEY |
| Green Building Final | 8/22/2023 | Approved | BOBBY KEY |
| HVAC-Final | 8/22/2023 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 8/22/2023 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 8/22/2023 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 8/22/2023 | Approved | BOBBY KEY |
| Final | 8/25/2023 | OK to Issue CofO | BOBBY KEY |
| HVAC-Final | 8/25/2023 | Approved | BOBBY KEY |