9010 N RESEDA BLVD 91324
Certificate Information: 9010 N RESEDA BLVD 91324
- Application / Permit
- 23016-20000-07995
- Plan Check / Job No.
- B23VN03459
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- Installation of 8 Electric Vehicle Charging Supercharging Stations for TESLA to include equipment anchorage & Parking Re-stripe. NO CHANGE IN PARKING
- Permit Issued
- Issued on 10/24/2025
- Issuing Office
- Current Status
- CofO Issued on 1/28/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/23/2023 | SERGIO GUTIERREZ |
| Corrections Issued | 4/26/2023 | SERGIO GUTIERREZ |
| Quality Review Completed | 5/1/2023 | RODOLFO ARIAS |
| Applicant returned to address corrections | 7/20/2023 | SERGIO GUTIERREZ |
| Plan Check Approved | 3/4/2024 | SERGIO GUTIERREZ |
| Issued | 10/24/2025 | APPLICANT |
| CofO in Progress | 1/27/2026 | DEANDRE HOFFMAN |
| Permit Finaled | 1/28/2026 | JEFFREY DURAN |
| CofO Issued | 1/28/2026 | JEFFREY DURAN |
| Permit Finaled | 1/28/2026 | JEFFREY DURAN |
Permit Application Clearance Information
| DAS Clearance | Cleared | 6/20/2023 | Hernan Arreola |
| Miscellaneous | Cleared | 6/29/2023 | NATHAN ROMINE |
| Prkng lot landscape/Water mgmt | Cleared | 6/29/2023 | NATHAN ROMINE |
| "Q" conditions | Cleared | 7/26/2023 | NATHAN ROMINE |
Contact Information
| Contractor | Solarcity Corporation; Lic. No.: 888104-C39 | , |
| Contractor | Tesla Energy Operations Inc; Lic. No.: 888104-C39 | , |
| Engineer | Voronov,, Kirill; Lic. No.: S6097 | PO BOX #458 TRINIDAD, CA 95570 |
Inspector Information
| EDWIN GREGORYONA, (818) 374-1105 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/13/2025 | Partial Inspection | DEANDRE HOFFMAN |
| Excavation/Setback/Form/Re-Bar | 12/8/2025 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Excavation/Setback/Form/Re-Bar | 12/16/2025 | Approved | GREGORY POMISH |
| Deputy Drilled-In Anchors | 12/30/2025 | Conditional Approval | DEANDRE HOFFMAN |
| Special/Order Compliance | 12/30/2025 | Partial Inspection | REGINA MENDEZ |
| Wall Anchors | 1/8/2026 | Corrections Issued | DEANDRE HOFFMAN |
| Final | 1/15/2026 | OK to Issue CofO | DEANDRE HOFFMAN |
| SGSOV-Seismic Gas S/O Valve | 1/15/2026 | SGSOV Approved | DEANDRE HOFFMAN |
| Smoke Detectors | 1/15/2026 | Approved | DEANDRE HOFFMAN |