12003 N SUSAN DR 91344

Certificate Information: 12003 N SUSAN DR 91344

Application / Permit
23016-20000-07962
Plan Check / Job No.
B23VN03443
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: ALQ/Storage conversion to ADU and addition to ADU to build a 657.4 sf ADU.. Per CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 12/28/2023
Issuing Office
Current Status
CofO Issued on 2/12/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/20/2023 APPLICANT
Assigned to Plan Check Engineer 3/24/2023 DAVID CASTILLO
Corrections Issued 3/25/2023 DAVID CASTILLO
Applicant returned to address corrections 4/19/2023 DAVID CASTILLO
Applicant returned to address corrections 4/29/2023 EDWIN ESPIN
Applicant returned to address corrections 5/16/2023 ALFREDO JARA
Applicant returned to address corrections 6/27/2023 ALFREDO JARA
Applicant returned to address corrections 8/30/2023 ALFREDO JARA
Plan Check Approved 11/28/2023 ALFREDO JARA
Issued 12/28/2023 APPLICANT
CofO in Progress 2/6/2026 CHRISTOPHER ROJAS
Permit Finaled 2/12/2026 RUBEN SALAS
Permit Finaled 2/12/2026 RUBEN SALAS
CofO Issued 2/12/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/5/2023 LEE GUILBEAUX
Sewer availability Cleared 4/5/2023 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 4/17/2023 LEE GUILBEAUX
Grading Pre-Inspection Cleared 11/21/2023 ROBERT HUGHES

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/5/2024 Partial Inspection JAVIER RAMOS JR
Pre-Inspection 6/5/2024 Approved JAVIER RAMOS JR
Deputy Drilled-In Anchors 6/12/2024 Conditional Approval JAVIER RAMOS JR
Deputy Drilled-In Anchors 8/8/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 9/9/2024 Approved ROBERT GOLD
ELECTRICAL-Rough 9/19/2024 Partial Approval JAVIER RAMOS JR
Insulation 9/19/2024 Partial Approval JAVIER RAMOS JR
Interior/Exterior Lathing 9/19/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 12/22/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Final 12/22/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Final 12/22/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Rough 12/22/2025 Not Ready for Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 12/22/2025 SGSOV Not Ready CHRISTOPHER ROJAS
Smoke Detectors 12/22/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Special/Order Compliance 12/22/2025 Corrections Issued CHRISTOPHER ROJAS
BUILDING-Rough-Frame 1/30/2026 Approved CHRISTOPHER ROJAS
Final 1/30/2026 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 1/30/2026 Approved CHRISTOPHER ROJAS
Green Building Rough 1/30/2026 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 1/30/2026 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 1/30/2026 Approved CHRISTOPHER ROJAS
Final 2/6/2026 OK to Issue CofO CHRISTOPHER ROJAS