6707 N DE CELIS PL 91406
Certificate Information: 6707 N DE CELIS PL 91406
- Application / Permit
- 23016-20000-07961
- Plan Check / Job No.
- B23VN03440
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: CONVERT (E) DETACHED GARAGE TO ADU PER GCS 65852.2(e)(1)(A) and WFPP
- Permit Issued
- Issued on 8/16/2023
- Issuing Office
- Current Status
- CofO Issued on 7/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/25/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2023 | JOHNPAUL ISIP |
| Corrections Issued | 4/1/2023 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 7/25/2023 | JOHNPAUL ISIP |
| Plan Check Approved | 8/11/2023 | DAVID CASTILLO |
| Issued | 8/16/2023 | APPLICANT |
| CofO in Progress | 7/18/2024 | RAUL OLAGI |
| Permit Finaled | 7/31/2024 | RUBEN SALAS |
| CofO Issued | 7/31/2024 | RUBEN SALAS |
| Permit Finaled | 7/31/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/15/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/15/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 4/19/2023 | CARLOS AGUILERA |
| ZI | Cleared | 6/9/2023 | STEVEN WECHSLER |
| Construction within easement | Cleared | 8/3/2023 | TINA MIRANDA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/19/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 9/19/2023 | Partial Approval | DAVID ANDERSON |
| BUILDING-Rough-Frame | 10/30/2023 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 10/30/2023 | Corrections Issued | RAUL OLAGI |
| HVAC-Rough | 10/30/2023 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 10/30/2023 | Corrections Issued | RAUL OLAGI |
| Sewer | 10/30/2023 | Partial Approval | RAUL OLAGI |
| Underground Mechanical | 10/30/2023 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 11/22/2023 | Partial Approval | RAUL OLAGI |
| Rough-Elec/Plmb/HVAC | 11/22/2023 | Approved | RAUL OLAGI |
| Shower Pan | 11/22/2023 | Approved | RAUL OLAGI |
| Underground Mechanical | 11/22/2023 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 12/7/2023 | Approved | RAUL OLAGI |
| Green Building Rough | 12/7/2023 | Approved | RAUL OLAGI |
| Insulation | 12/7/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 12/8/2023 | Approved | RAUL OLAGI |
| Drywall Nailing | 12/13/2023 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 3/18/2024 | Corrections Issued | RAUL OLAGI |
| Final | 3/18/2024 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 3/18/2024 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Final | 3/18/2024 | Corrections Issued | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 3/18/2024 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 3/18/2024 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 4/24/2024 | Approved | RAUL OLAGI |
| HVAC-Final | 4/24/2024 | Approved | RAUL OLAGI |
| PLUMBING-Final | 4/24/2024 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 7/18/2024 | Approved | RAUL OLAGI |
| Final | 7/18/2024 | OK to Issue CofO | RAUL OLAGI |
| Smoke Detectors | 7/18/2024 | Approved | RAUL OLAGI |