6707 N DE CELIS PL 91406

Certificate Information: 6707 N DE CELIS PL 91406

Application / Permit
23016-20000-07961
Plan Check / Job No.
B23VN03440
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: CONVERT (E) DETACHED GARAGE TO ADU PER GCS 65852.2(e)(1)(A) and WFPP
Permit Issued
Issued on 8/16/2023
Issuing Office
Current Status
CofO Issued on 7/31/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/25/2023 APPLICANT
Assigned to Plan Check Engineer 3/31/2023 JOHNPAUL ISIP
Corrections Issued 4/1/2023 JOHNPAUL ISIP
Applicant returned to address corrections 7/25/2023 JOHNPAUL ISIP
Plan Check Approved 8/11/2023 DAVID CASTILLO
Issued 8/16/2023 APPLICANT
CofO in Progress 7/18/2024 RAUL OLAGI
Permit Finaled 7/31/2024 RUBEN SALAS
CofO Issued 7/31/2024 RUBEN SALAS
Permit Finaled 7/31/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/15/2023 CARLOS AGUILERA
Sewer availability Cleared 4/15/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 4/19/2023 CARLOS AGUILERA
ZI Cleared 6/9/2023 STEVEN WECHSLER
Construction within easement Cleared 8/3/2023 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/19/2023 Approved DAVID ANDERSON
PLUMBING-Rough 9/19/2023 Partial Approval DAVID ANDERSON
BUILDING-Rough-Frame 10/30/2023 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 10/30/2023 Corrections Issued RAUL OLAGI
HVAC-Rough 10/30/2023 Corrections Issued RAUL OLAGI
PLUMBING-Rough 10/30/2023 Corrections Issued RAUL OLAGI
Sewer 10/30/2023 Partial Approval RAUL OLAGI
Underground Mechanical 10/30/2023 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 11/22/2023 Partial Approval RAUL OLAGI
Rough-Elec/Plmb/HVAC 11/22/2023 Approved RAUL OLAGI
Shower Pan 11/22/2023 Approved RAUL OLAGI
Underground Mechanical 11/22/2023 Approved RAUL OLAGI
BUILDING-Rough-Frame 12/7/2023 Approved RAUL OLAGI
Green Building Rough 12/7/2023 Approved RAUL OLAGI
Insulation 12/7/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 12/8/2023 Approved RAUL OLAGI
Drywall Nailing 12/13/2023 Approved RAUL OLAGI
ELECTRICAL-Final 3/18/2024 Corrections Issued RAUL OLAGI
Final 3/18/2024 Corrections Issued RAUL OLAGI
Green Building Final 3/18/2024 Corrections Issued RAUL OLAGI
PLUMBING-Final 3/18/2024 Corrections Issued RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 3/18/2024 SGSOV Approved RAUL OLAGI
Smoke Detectors 3/18/2024 Corrections Issued RAUL OLAGI
Green Building Final 4/24/2024 Approved RAUL OLAGI
HVAC-Final 4/24/2024 Approved RAUL OLAGI
PLUMBING-Final 4/24/2024 Approved RAUL OLAGI
ELECTRICAL-Final 7/18/2024 Approved RAUL OLAGI
Final 7/18/2024 OK to Issue CofO RAUL OLAGI
Smoke Detectors 7/18/2024 Approved RAUL OLAGI