12578 N HERRICK AVE 91342
Certificate Information: 12578 N HERRICK AVE 91342
- Application / Permit
- 23016-20000-07896
- Plan Check / Job No.
- B23VN03417
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EX DETACHED 22'5"X24'2" GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (d). CONSTRUCTION DESIGN PER ENGR.
- Permit Issued
- Issued on 7/6/2023
- Issuing Office
- Valley
- Current Status
- Issued on 7/6/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/22/2023 | SERGIO MUNIZ |
| Corrections Issued | 3/23/2023 | SERGIO MUNIZ |
| Building Plans Picked Up | 3/28/2023 | APPLICANT |
| Applicant returned to address corrections | 6/27/2023 | HAYATO TSUCHIYA |
| Plan Check Approved | 7/3/2023 | ISIS ARGUETA |
| Issued | 7/6/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/31/2023 | FERNANDO GIL |
| Sewer availability | Cleared | 3/31/2023 | FERNANDO GIL |
| Eng Process Fee Ord 176,300 | Cleared | 4/14/2023 | FERNANDO GIL |
| Construction near power lines | Cleared | 6/23/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Ivy Green Construction; Lic. No.: 1014647-B | 14537 VENTURA BLVD SHERMAN OAKS, CA 91403 |
| Engineer | Valencia,, Byron Steve; Lic. No.: C87372 | 14537 VENTURA BLVD SHERMAN OAKS, CA 91403 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/21/2023 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 7/21/2023 | Corrections Issued | RAUL OLAGI |
| Deputy Drilled-In Anchors | 8/17/2023 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 8/25/2023 | Corrections Issued | ROBERT GOLD |
| Green Building Rough | 8/25/2023 | Not Ready for Inspection | ROBERT GOLD |
| Rough-Elec/Plmb/HVAC | 8/25/2023 | Corrections Issued | ROBERT GOLD |
| BUILDING-Rough-Frame | 8/30/2023 | Corrections Issued | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2023 | Partial Approval | DAVID MATSON |
| Green Building Rough | 8/30/2023 | Approved | DAVID MATSON |
| Rough-Elec/Plmb/HVAC | 8/30/2023 | Not Ready for Inspection | DAVID MATSON |
| Insulation | 10/2/2023 | Not Ready for Inspection | KEVIN BERBERYAN |
| Drywall Nailing | 10/5/2023 | Approved | KEVIN BERBERYAN |
| Rough-Elec/Plmb/HVAC | 10/5/2023 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 4/17/2024 | Approved | KEVIN BERBERYAN |
| Final | 4/17/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Green Building Final | 4/17/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 4/17/2024 | SGSOV Not Ready | KEVIN BERBERYAN |
| Service/Power Release | 4/17/2024 | Corrections Issued | KEVIN BERBERYAN |
| Smoke Detectors | 4/17/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 4/24/2024 | SGSOV Not Ready | KEVIN BERBERYAN |
| Final | 5/17/2024 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 5/17/2024 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 5/17/2024 | SGSOV Not Ready | KEVIN BERBERYAN |
| Smoke Detectors | 5/17/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Underground Mechanical | 5/17/2024 | Approved | KEVIN BERBERYAN |
| Final | 6/6/2024 | No Access for Inspection | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 6/6/2024 | SGSOV Not Ready | KEVIN BERBERYAN |
| Smoke Detectors | 6/6/2024 | No Access for Inspection | KEVIN BERBERYAN |