10935-10937 N COLLETT AVE 91344

Certificate Information: 10935-10937 N COLLETT AVE 91344

Application / Permit
23016-20000-07766
Plan Check / Job No.
B23VN03362
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT ATTACHED GARAGE INTO JUNIOR ACCESSORY DWELLING UNIT PER CA GOVT. CODE 65852.2(e)(1)(A) AND 65852.22. WORK PER WFPP.
Permit Issued
Issued on 4/18/2023
Issuing Office
Current Status
CofO Issued on 4/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/17/2023 APPLICANT
Assigned to Plan Check Engineer 3/23/2023 ROSENDO MEDINA
Corrections Issued 3/29/2023 ROSENDO MEDINA
Plan Check Approved 4/18/2023 ROSENDO MEDINA
Issued 4/18/2023 APPLICANT
CofO in Progress 3/22/2024 JAVIER RAMOS JR
Permit Finaled 4/30/2024 RUBEN SALAS
CofO Issued 4/30/2024 RUBEN SALAS
Permit Finaled 4/30/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/31/2023 FERNANDO GIL
Sewer availability Cleared 3/31/2023 FERNANDO GIL
Eng Process Fee Ord 176,300 Cleared 4/3/2023 FERNANDO GIL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/11/2023 Conditional Approval MICHAEL SMITH
Footing/Foundation/Slab 6/5/2023 Approved JAVIER RAMOS JR
PLUMBING-Rough 6/5/2023 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 6/29/2023 Not Ready for Inspection DAVID ANDERSON
Deputy Drilled-In Anchors 6/29/2023 Conditional Approval ROBERT GOLD
Deputy Wood Construction 6/29/2023 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 6/29/2023 Partial Approval DAVID ANDERSON
Gas Test 6/29/2023 Approved DAVID ANDERSON
Interior/Exterior Lathing 6/29/2023 Approved DAVID ANDERSON
MERV13>=Rough 6/29/2023 Approved DAVID ANDERSON
PLUMBING-Rough 6/29/2023 Corrections Issued DAVID ANDERSON
Underground Mechanical 6/29/2023 Partial Approval DAVID ANDERSON
BUILDING-Rough-Frame 8/7/2023 Not Ready for Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 8/7/2023 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 8/7/2023 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 10/16/2023 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Rough 10/16/2023 Approved JAVIER RAMOS JR
HVAC-Rough 10/16/2023 Approved JAVIER RAMOS JR
Insulation 10/16/2023 Approved JAVIER RAMOS JR
PLUMBING-Rough 10/16/2023 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 12/1/2023 Partial Inspection JAVIER RAMOS JR
Drywall Nailing 12/1/2023 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 12/1/2023 Corrections Issued JAVIER RAMOS JR
Shower Pan 12/1/2023 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 3/8/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Final 3/8/2024 Approved JAVIER RAMOS JR
Final 3/8/2024 Corrections Issued JAVIER RAMOS JR
MERV13>=Final 3/8/2024 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 3/8/2024 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 3/8/2024 Approved JAVIER RAMOS JR
Final 3/21/2024 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 3/21/2024 Approved JAVIER RAMOS JR
HVAC-Final 3/21/2024 Approved JAVIER RAMOS JR
PLUMBING-Final 3/21/2024 Approved JAVIER RAMOS JR