1931 S FEDERAL AVE 90025

Certificate Information: 1931 S FEDERAL AVE 90025

Application / Permit
23016-20000-07272
Plan Check / Job No.
B23VN03158
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DET GARAGE AND ATT LAUNDRY ROOM TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 3/24/2023
Issuing Office
Valley
Current Status
CofO Issued on 4/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/13/2023 APPLICANT
Assigned to Plan Check Engineer 3/16/2023 JESSE ARELLANO
Corrections Issued 3/18/2023 JESSE ARELLANO
Building Plans Picked Up 3/20/2023 APPLICANT
Plan Check Approved 3/23/2023 MOHAMMAD ESMAILI
Issued 3/24/2023 APPLICANT
CofO in Progress 11/26/2024 ARAM AVEDISIAN
No Progress 11/27/2024 KENNETH NAGLE
CofO in Progress 11/27/2024 KENNETH NAGLE
Permit Finaled 4/30/2025 RICHARD STEINBACH
CofO Issued 4/30/2025 RICHARD STEINBACH
Permit Finaled 4/30/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 3/21/2023 JASON NG
Eng Process Fee Ord 176,300 Cleared 3/21/2023 JASON NG
Sewer availability Cleared 3/21/2023 JASON NG
Specific Plan Cleared 3/21/2023 ALESSANDRO MERCURI

Contact Information

Contractor Progressive Construction Inc; Lic. No.: 1024265-B 1522 16TH STREET      SANTA MONICA, CA 90404

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/30/2023 Partial Approval CLAYTON GRAHAM
Underground Mechanical 3/30/2023 Partial Approval CLAYTON GRAHAM
Footing/Foundation/Slab 4/11/2023 Approved JEREMY TODD
Underground Mechanical 4/11/2023 Approved JEREMY TODD
ELECTRICAL-Rough 4/21/2023 Corrections Issued JESUS PINEDA
Gas Test 4/21/2023 Partial Approval JESUS PINEDA
HVAC-Rough 4/21/2023 Approved JESUS PINEDA
PLUMBING-Rough 4/21/2023 Approved JESUS PINEDA
Wood Frame 4/21/2023 Partial Approval JESUS PINEDA
BUILDING-Rough-Frame 4/25/2023 Approved JESUS PINEDA
ELECTRICAL-Rough 4/25/2023 Approved JESUS PINEDA
Green Building Rough 4/25/2023 Approved JESUS PINEDA
Insulation 4/25/2023 Approved JESUS PINEDA
Interior/Exterior Lathing 4/25/2023 Approved JESUS PINEDA
Shower Pan 4/25/2023 Approved JESUS PINEDA
Drywall Nailing 5/2/2023 Approved ASHLEY THOMPSON
ELECTRICAL-Final 7/31/2023 Corrections Issued CHRISTOPHER WILSON
Final 7/31/2023 Corrections Issued CHRISTOPHER WILSON
Green Building Final 7/31/2023 Approved CHRISTOPHER WILSON
HVAC-Final 7/31/2023 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Final 7/31/2023 Corrections Issued CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 7/31/2023 SGSOV Approved CHRISTOPHER WILSON
Smoke Detectors 7/31/2023 Approved CHRISTOPHER WILSON
ELECTRICAL-Final 1/25/2024 Approved BEN MOLSTAD
Final 1/25/2024 Not Ready for Inspection BEN MOLSTAD
HVAC-Final 1/25/2024 Not Ready for Inspection BEN MOLSTAD
PLUMBING-Final 1/25/2024 Approved BEN MOLSTAD
Final 11/21/2024 Corrections Issued KIRK SANDERS
Final 11/26/2024 OK to Issue CofO ARAM AVEDISIAN
Special/Order Compliance 12/9/2024 Corrections Issued KENNETH NAGLE