8101-8103 N MELBA AVE 91304

Certificate Information: 8101-8103 N MELBA AVE 91304

Application / Permit
23016-20000-07141
Plan Check / Job No.
B23VN03102
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 21'4" X 22' GARAGE TO (N) JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) and 65852.22. WORK DONE PER ENGINEERING.
Permit Issued
Issued on 4/10/2023
Issuing Office
Current Status
CofO Issued on 12/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/12/2023 APPLICANT
Assigned to Plan Check Engineer 3/16/2023 MADISON ODELL
Corrections Issued 3/17/2023 MADISON ODELL
Applicant returned to address corrections 3/30/2023 MADISON ODELL
Plan Check Approved 4/10/2023 MADISON ODELL
Issued 4/10/2023 APPLICANT
CofO in Progress 12/13/2023 CHRIS CHRISTENSEN
Permit Finaled 12/27/2023 JOHN JANSON
CofO Issued 12/27/2023 JOHN JANSON
Permit Finaled 12/27/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/28/2023 RYAN KIM
Sewer availability Cleared 3/28/2023 RYAN KIM
Eng Process Fee Ord 176,300 Cleared 3/29/2023 RYAN KIM
Grading Pre-Inspection Cleared 4/9/2023 MADISON ODELL

Contact Information

Contractor Owner-Builder       ,
Engineer Mohammadi,, Saeid; Lic. No.: NA82330       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/11/2023 Conditional Approval CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 4/18/2023 Conditional Approval CHRIS CHRISTENSEN
PLUMBING-Rough 4/18/2023 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 5/3/2023 Corrections Issued CHRIS CHRISTENSEN
PLUMBING-Rough 5/3/2023 Corrections Issued CHRIS CHRISTENSEN
Wood Frame 5/3/2023 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 5/5/2023 Approved CHRIS CHRISTENSEN
Rough-Elec/Plmb/HVAC 5/5/2023 Approved CHRIS CHRISTENSEN
Shower Pan 5/5/2023 Approved CHRIS CHRISTENSEN
HVAC-Rough 5/10/2023 Approved CHRIS CHRISTENSEN
Insulation 5/10/2023 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 5/10/2023 Partial Approval CHRIS CHRISTENSEN
Drywall Nailing 5/22/2023 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 5/22/2023 Approved CHRIS CHRISTENSEN
Shower Pan 5/22/2023 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 10/4/2023 Approved CHRIS CHRISTENSEN
Final 10/4/2023 Corrections Issued CHRIS CHRISTENSEN
Gas Test 10/4/2023 Approved CHRIS CHRISTENSEN
PLUMBING-Final 10/4/2023 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 10/4/2023 SGSOV Not Ready CHRIS CHRISTENSEN
Service/Power Release 10/4/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Smoke Detectors 10/4/2023 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 10/18/2023 Approved CHRIS CHRISTENSEN
Final 10/18/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Gas Test 10/18/2023 Approved CHRIS CHRISTENSEN
HVAC-Final 10/18/2023 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Final 10/18/2023 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 10/18/2023 SGSOV Approved CHRIS CHRISTENSEN
Service/Power Release 10/18/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Final 10/31/2023 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Final 10/31/2023 Approved CHRIS CHRISTENSEN
Final 12/12/2023 OK to Issue CofO CHRIS CHRISTENSEN