16622-16624 W BAHAMA ST 91343

Certificate Information: 16622-16624 W BAHAMA ST 91343

Application / Permit
23016-20000-07088
Plan Check / Job No.
B23VN03076
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK DONE PER WFPP.
Permit Issued
Issued on 3/21/2023
Issuing Office
Current Status
Issued on 3/21/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/10/2023 APPLICANT
Assigned to Plan Check Engineer 3/15/2023 ARTIN ZARUKIAN
Corrections Issued 3/18/2023 ARTIN ZARUKIAN
Building Plans Picked Up 3/20/2023 APPLICANT
Plan Check Approved 3/21/2023 ALEC MOUSAKHANIAN
Issued 3/21/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/21/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/21/2023 CARLOS AGUILERA
Sewer availability Cleared 3/21/2023 CARLOS AGUILERA
Hold Cleared 5/30/2023 MARIA VENDIVIL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/1/2023 Partial Approval RAUL OLAGI
Sewer 6/1/2023 Approved RAUL OLAGI
Deputy Drilled-In Anchors 6/5/2023 Conditional Approval MICHAEL SMITH
Footing/Foundation/Slab 6/6/2023 Approved ROBERT GOLD
Deputy Reinf. Concrete 6/14/2023 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 7/6/2023 Not Ready for Inspection RAUL OLAGI
ELECTRICAL-Rough 10/18/2023 Approved RAUL OLAGI
PLUMBING-Rough 10/18/2023 Approved RAUL OLAGI
Insulation 11/6/2024 Corrections Issued GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 11/25/2024 Corrections Issued SALVADOR MARTINEZ
BUILDING-Rough-Frame 12/26/2024 Approved RAUL OLAGI
HVAC-Rough 12/26/2024 Partial Approval RAUL OLAGI
HVAC-Rough 1/3/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 1/3/2025 Partial Approval GAREN HAYRAPETYAN
Insulation 1/8/2025 Not Ready for Inspection LOUIS ESCOTO
Shower Pan 1/8/2025 Approved LOUIS ESCOTO
Insulation 1/31/2025 Partial Approval SALVADOR MARTINEZ
Green Building Rough 2/13/2025 Approved SALVADOR MARTINEZ
Insulation 2/13/2025 Approved SALVADOR MARTINEZ
Drywall Nailing 9/5/2025 Approved GAREN HAYRAPETYAN