14519 W SYLVAN ST 91411
Certificate Information: 14519 W SYLVAN ST 91411
- Application / Permit
- 23016-20000-07047
- Plan Check / Job No.
- B23VN03055
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (6) Church
- Work Description
- CHANGE OF USE TO CONVERT PRIVATE SCHOOL TO PART OF THE EXISTING CHURCH
- Permit Issued
- Issued on 8/16/2023
- Issuing Office
- Current Status
- Issued on 8/16/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/16/2023 | MARVEL DELACRUZ |
| Corrections Issued | 3/18/2023 | MARVEL DELACRUZ |
| Quality Review Completed | 3/28/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 3/28/2023 | APPLICANT |
| Disabled Access Plans Picked Up | 3/29/2023 | APPLICANT |
| Applicant returned to address corrections | 6/23/2023 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 8/10/2023 | MARVEL DELACRUZ |
| Plan Check Approved | 8/10/2023 | MARVEL DELACRUZ |
| Issued | 8/16/2023 | APPLICANT |
Permit Application Clearance Information
| "Q" conditions | Cleared | 4/5/2023 | MAYELA VILLA |
| Comm Cor/Mini-Mall | Cleared | 4/5/2023 | MAYELA VILLA |
| Miscellaneous | Cleared | 4/5/2023 | MAYELA VILLA |
| Eng Process Fee Ord 176,300 | Cleared | 4/6/2023 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 4/8/2023 | MARKOS PEREZ-BRAN |
| ZI | Cleared | 4/11/2023 | JOANNA MARROQUIN |
| Fire Marshal Fire Life Safety | Cleared | 6/13/2023 | ANDREW KO |
| DAS Clearance | Cleared | 6/28/2023 | MARVEL DELACRUZ |
| Miscellaneous | Cleared | 7/13/2023 | NELSON RODRIGUEZ |
Contact Information
| Contractor | Moda Construction; Lic. No.: 1029865-B | 38256 MENDOCINO WAY PALMDALE, CA 93550 |
| Engineer | Teng,, Dai; Lic. No.: C86084 | 422 FALLINGSTAR IRVINE, CA 92614 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 8/22/2023 | Conditional Approval | CAMERON CHABAN |
| Special/Order Compliance | 12/23/2024 | Partial Inspection | BRIAN KELLY |
| Special/Order Compliance | 3/20/2025 | Partial Inspection | BRIAN KELLY |
| Pre-Inspection | 7/2/2025 | Corrections Issued | BRIAN KELLY |
| Special/Order Compliance | 7/2/2025 | Partial Inspection | ROBERT DAVIS |