1141-1143 W 59TH ST 90044

Certificate Information: 1141-1143 W 59TH ST 90044

Application / Permit
23016-20000-07046
Plan Check / Job No.
B23VN03054
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT EXISTING 1ST STORY GARAGE WITHIN (E) GARAGE W/ SECOND STORY UNIT INTO (N) 490 SF ADU PER GCS 65852.2(e)(1)(A) ALL WORK PER ENG.
Permit Issued
Issued on 4/26/2023
Issuing Office
Valley
Current Status
CofO Issued on 9/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/10/2023 APPLICANT
Assigned to Plan Check Engineer 3/16/2023 JESSE ARELLANO
Corrections Issued 3/17/2023 JESSE ARELLANO
Building Plans Picked Up 3/21/2023 APPLICANT
Plan Check Approved 4/26/2023 LUISANGEL VALENZUELA
Issued 4/26/2023 APPLICANT
CofO in Progress 8/7/2025 BARRY HACHE
No Progress 9/1/2025 DEROLD HAUFF
CofO in Progress 9/1/2025 DEROLD HAUFF
Permit Finaled 9/11/2025 DEROLD HAUFF
CofO Issued 9/11/2025 DEROLD HAUFF
Permit Finaled 9/11/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/4/2023 ADRIAN SANCHEZ
Sewer availability Cleared 4/4/2023 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 4/7/2023 ADRIAN SANCHEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Sabzehzar,, Habib; Lic. No.: C50442 8180 N PRICE AVE      FRESNO, CA 93720

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 9/11/2024 Corrections Issued CRAIG DAVIS
ELECTRICAL-Rough 10/21/2024 Partial Approval CRAIG DAVIS
Deputy Drilled-In Anchors 10/23/2024 Conditional Approval JOSH MEISTER
Footing/Foundation/Slab 10/23/2024 Corrections Issued BRENDAN MORELLI
PLUMBING-Rough 10/24/2024 Partial Approval CRAIG DAVIS
BUILDING-Rough-Frame 11/1/2024 Not Ready for Inspection CRAIG DAVIS
Green Building Rough 11/1/2024 Not Ready for Inspection CRAIG DAVIS
ELECTRICAL-Rough 11/12/2024 Corrections Issued CRAIG DAVIS
HVAC-Rough 11/12/2024 Corrections Issued CRAIG DAVIS
Insulation 11/12/2024 Corrections Issued CRAIG DAVIS
PLUMBING-Rough 11/12/2024 Corrections Issued CRAIG DAVIS
Insulation 11/20/2024 Partial Inspection ANTHONY RAMOS
BUILDING-Rough-Frame 11/22/2024 Corrections Issued JOSE MACIAS
ELECTRICAL-Rough 11/22/2024 Corrections Issued JOSE MACIAS
Green Building Rough 11/22/2024 Corrections Issued JOSE MACIAS
HVAC-Rough 11/22/2024 Corrections Issued JOSE MACIAS
Insulation 11/22/2024 Corrections Issued JOSE MACIAS
PLUMBING-Rough 11/22/2024 Approved JOSE MACIAS
Interior/Exterior Lathing 11/26/2024 Approved CRAIG DAVIS
Drywall Nailing 12/3/2024 Approved JOSE MACIAS
ELECTRICAL-Rough 12/16/2024 Approved BARRY HACHE
BUILDING-Rough-Frame 2/26/2025 Approved BARRY HACHE
Final 2/26/2025 Corrections Issued BARRY HACHE
Green Building Final 2/26/2025 Corrections Issued BARRY HACHE
Green Building Rough 2/26/2025 Approved BARRY HACHE
SGSOV-Seismic Gas S/O Valve 2/26/2025 SGSOV Not Ready BARRY HACHE
Smoke Detectors 2/26/2025 Not Ready for Inspection BARRY HACHE
ELECTRICAL-Final 3/14/2025 Corrections Issued BARRY HACHE
Gas Test 3/14/2025 Approved BARRY HACHE
HVAC-Final 3/14/2025 Corrections Issued BARRY HACHE
PLUMBING-Final 3/14/2025 Approved BARRY HACHE
SGSOV-Seismic Gas S/O Valve 3/14/2025 SGSOV Approved BARRY HACHE
ELECTRICAL-Final 4/29/2025 Approved BARRY HACHE
Green Building Final 4/29/2025 Approved BARRY HACHE
HVAC-Final 4/29/2025 Approved BARRY HACHE
ELECTRICAL-Final 6/4/2025 Approved BARRY HACHE
Final 6/4/2025 Corrections Issued BARRY HACHE
Service/Power Release 6/4/2025 Not Ready for Inspection BARRY HACHE
Smoke Detectors 6/4/2025 Approved BARRY HACHE
Final 8/1/2025 Conditional Approval BARRY HACHE
Final 8/7/2025 OK to Issue CofO BARRY HACHE
Special/Order Compliance 9/2/2025 Approved BARRY HACHE