10514 N SHOSHONE AVE 91344

Certificate Information: 10514 N SHOSHONE AVE 91344

Application / Permit
23016-20000-07021
Plan Check / Job No.
B23VN03036
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPlan: Convert Covered Patio to (N) Master Bedroom
Permit Issued
Issued on 7/20/2023
Issuing Office
Current Status
CofO Issued on 12/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/29/2023 APPLICANT
Assigned to Plan Check Engineer 3/30/2023 JOHNPAUL ISIP
Corrections Issued 3/30/2023 JOHNPAUL ISIP
Applicant returned to address corrections 5/4/2023 DAVID CASTILLO
Applicant returned to address corrections 6/16/2023 JASON JANGADA
Applicant returned to address corrections 6/17/2023 JASON JANGADA
Applicant returned to address corrections 7/14/2023 JASON JANGADA
Plan Check Approved 7/18/2023 EDWIN ESPIN
Issued 7/20/2023 APPLICANT
CofO in Progress 11/27/2024 JAVIER RAMOS JR
Permit Finaled 12/4/2024 RUBEN SALAS
CofO Issued 12/4/2024 RUBEN SALAS
Permit Finaled 12/4/2024 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/3/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 5/4/2023 NIKKI ZULUETA
ZI Cleared 6/14/2023 ALEX VELA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/26/2023 Approved JAVIER RAMOS JR
PLUMBING-Rough 10/4/2023 Not Ready for Inspection JAVIER RAMOS JR
Sewer 10/4/2023 Not Ready for Inspection JAVIER RAMOS JR
Wood Frame 10/4/2023 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 10/12/2023 Partial Approval JAVIER RAMOS JR
Insulation 10/12/2023 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 10/12/2023 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 11/6/2023 Partial Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 11/6/2023 Corrections Issued JAVIER RAMOS JR
HVAC-Rough 11/6/2023 Approved JAVIER RAMOS JR
PLUMBING-Rough 11/6/2023 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 11/15/2023 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 11/15/2023 Approved JAVIER RAMOS JR
Insulation 11/15/2023 Approved JAVIER RAMOS JR
Shower Pan 11/15/2023 Approved JAVIER RAMOS JR
Drywall Nailing 11/22/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 11/22/2023 Not Ready for Inspection MICHEL ABAJAN
Interior/Exterior Lathing 11/29/2023 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 2/16/2024 Approved JAVIER RAMOS JR
Final 2/16/2024 Corrections Issued JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 2/16/2024 SGSOV Not Ready JAVIER RAMOS JR
Smoke Detectors 2/16/2024 Not Ready for Inspection JAVIER RAMOS JR
Final 4/5/2024 Corrections Issued JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 4/5/2024 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 4/5/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Final 9/26/2024 Approved JAVIER RAMOS JR
Final 9/26/2024 OK to Issue CofO JAVIER RAMOS JR